Forum » CS-2009 EAc5.1
Topic

M&V Plan- Specific Acceptable Range(s) of Error

CS-2009 EAc5.1: Measurement and verification - base building
posted by Marina Andrade on Dec 20, 2012, 2:07 pm

Hello,

I just got the review comment requesting the “specific acceptable range(s) of error”, follow the comment bellow.

“TECHNICAL ADVICE:

Please revise the Measurement and...

Last reply: Marina Andrade, Dec 21, 2012, 6:40 am

submit to leed-online compliance

CS-2009 EAc5.1: Measurement and verification - base building
posted by Ron Dean on Dec 10, 2012, 11:07 am

Good day,

i wonder what is the time that I can submit the M&V plan for credit 5.1.
May I submit it when the construccion is finished with the rest of the credits for C&S...

Last reply: Marcus Sheffer, Dec 10, 2012, 11:30 am

What to measure?

CS-2009 EAc5.1: Measurement and verification - base building
posted by Marcio Alberto Casado Pereira on Oct 16, 2012, 3:15 pm

We are working on a multiple building campus, it's a residential project. We want to pursue EAc5.1 but we are not sure of which loads should be measured; since is a C&S, we understand that we...

Last reply: Marcus Sheffer, Oct 16, 2012, 4:42 pm

EAc 5.1 for CS tenant spaces

CS-2009 EAc5.1: Measurement and verification - base building
posted by charles bell on Sep 26, 2012, 2:38 pm

Our current design has a Quadlogic multi-tenant smart meter unit in the basement of our mid-rise project. This unit has the capacity for electrical power as well as BTU monitoring. My question...

Last reply: Marcus Sheffer, Sep 26, 2012, 4:22 pm

Lighting measurement

CS-2009 EAc5.1: Measurement and verification - base building
posted by Ron Dean on Aug 24, 2012, 11:34 am

good day,
I have a project with 14 floors and our project scope is to control the hall and restroom lighting, we can measure and verify their savings.
I have a doubt about what I need...

Last reply: Marcus Sheffer, Aug 27, 2012, 10:18 am

Tenant Submetering connected to BMS?

CS-2009 EAc5.1: Measurement and verification - base building
posted by Marco Abdallah on Aug 24, 2012, 4:56 am

We are pursueing 5.1 Opt. 1 and 5.2 at a CS-project with 10 floors leasable to different tenants. The electricity metering is not clear for me:

The RG says on page 317 that the monitoring...

Last reply: Marcus Sheffer, Aug 24, 2012, 8:58 am

M&V period for LEED 2009 C&S projects for EAc5.1 + EAc5.2

CS-2009 EAc5.1: Measurement and verification - base building
posted by Philip Herriges on Jul 17, 2012, 11:16 am

The LEED reference guide is very particular in the language that they use to describe the intent and stragegies for EAc5.1 and 5.2 for C&S as being distinct from NC & Schools.

For...

Last reply: Marcus Sheffer, Jul 17, 2012, 12:26 pm

Calibration to actual energy use??

CS-2009 EAc5.1: Measurement and verification - base building
posted by javier bolanos zeledon on Dec 13, 2010, 5:20 am

Hi, I don't understand why the reference guide is asking to calibrate the as-built simulation model to the actual energy use. In a new construction there is no actual energy use yet, unless you...

Last reply: Marcus Sheffer, Jun 26, 2012, 8:42 pm

Core & Shell M&V

CS-2009 EAc5.1: Measurement and verification - base building
posted by Randy Cook on Mar 2, 2012, 2:50 pm

Hello, I have read thru the previous posts and responses, and hope this is not a redundant question. I am working on a C&S major renovation. We are going to follow Option B from...

Last reply: Marcus Sheffer, Mar 2, 2012, 5:13 pm

Extra Point = Building Performance Partnership

CS-2009 EAc5.1: Measurement and verification - base building
posted by Alison Y Rivenburgh on May 17, 2010, 4:57 pm

From the USGBC website:
"LEED 2009 for New Construction, LEED 2009 for Core & Shell, or LEED 2009 for Schools projects that participate in BPP Data Collection Phase 1 and signing a...

Last reply: Marcus Sheffer, Dec 1, 2011, 1:40 pm