Log in
Forum » CS-2009 EAc1
Topic

Credit "Optimize Energy Performance" in Appeal Phase

CS-2009 EAc1: Optimize Energy Performance
posted by Florian Schmidtchen on Nov 10, 2010, 2:57 am

We are managing the certification of an office building according LEED C&S 2009. Due to contractual reasons, the building owner has to reach LEED silver to sell the building to his client....

Last reply: Marcus Sheffer, Nov 10, 2010, 9:04 am

Envelope mandatory provisions

CS-2009 EAc1: Optimize Energy Performance
posted by javier bolanos zeledon on Oct 24, 2010, 7:18 pm

According to Ashrae 90.1-2007 art 5.4.1 where insulation is required in sections 5.5 or 5.6 it shall comply with 5.8.1.1-5.8.1.9. What is not clear to me is if you have to comply with the...

Last reply: javier bolanos zeledon, Oct 25, 2010, 12:07 pm

Hot and humid area

CS-2009 EAc1: Optimize Energy Performance
posted by javier bolanos zeledon on Oct 15, 2010, 12:03 am

I have a CS V2.0 office building project in a hot an humid area, climate zone 3C as per Ashrae.
According to our project size and characteristics the baseline system that should be designed...

Last reply: javier bolanos zeledon, Oct 18, 2010, 11:15 am

LEED-CS Multiple Building Energy Approach

CS-2009 EAc1: Optimize Energy Performance
posted by Edwin Wealend on Sep 7, 2010, 2:27 am

Hi does anyone have access to the potential LEED Multiple Building guideline for v3 projects, in particular the energy EA-1 ASHRAE requirements?

We have a project at a critical stage and...

Last reply: Christopher Schaffner, Sep 8, 2010, 11:12 am

Apartment-office building in China

CS-2009 EAc1: Optimize Energy Performance
posted by Ran Zhang on Aug 30, 2010, 10:45 am

The project I am working on has three building as a whole. These three buildings will be defined as office use but designed as apartment style. It is defined as apartment-office building in...

Last reply: Christopher Schaffner, Aug 31, 2010, 4:30 pm

TENANT SPACE ENERGY MODELING

CS-2009 EAc1: Optimize Energy Performance
posted by javier bolanos zeledon on Jun 29, 2010, 11:19 am

I'm modeling a CS office building, but have no tenants yet. It is my understanding that I have to provide tenant HVAC equipment as per baseline building requirements to the design building, in...

Last reply: Christopher Schaffner, Jul 19, 2010, 8:45 pm

Modelling a project with 3 buildings

CS-2009 EAc1: Optimize Energy Performance
posted by Maya Karkour on Apr 30, 2010, 10:39 am

Hi,
We need to undertake the Whole Building Simulation option for a school project which consists of 3 buildings on the same site - and part of the same LEED certification. The buildings...

Last reply: Tristan Roberts, May 3, 2010, 1:36 pm

Energy Modelling for a Natually Ventilated residential Bldg

CS-2009 EAc1: Optimize Energy Performance
posted by ESD Surbana on Feb 4, 2010, 3:19 am

Hi,

I am currently working on LEED CS V2.2 certification for a Residential building in Malaysia and I am facing a problem with the energy modelling.

The air conditioning system...

Last reply: Rob Watson, Mar 30, 2010, 2:25 pm