Option 1: Full Flush-out Before Occupancy- Is there a Min. CF?CI-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by Michelle Bracewell-Musson on Aug 4, 2011, 10:50 am
With Option 1, Path 1, we are expected to flush-out 14,000 cf/sf of outdoor air at 60 degrees temp. and 60% humidity min. Is there a minimum ventilation rate as with Path 2 which is 0.30 cf/min... Last reply: Dylan Connelly, Sep 22, 2011, 11:37 am |
|
Phased Occupancy and IAQ TestingCI-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by Melissa Wrolstad on Feb 22, 2011, 5:11 pm
I have a CI project with 4 floors and phased occupancy. Two floors will be occupied while two are still under construction. Is it possible to split... Last reply: Susann Geithner, Feb 24, 2011, 9:53 am |
|
Staged Move in and Natural VentilationCI-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by Sam Keehn on Feb 9, 2011, 6:26 am
We are working on an office fit (3,800ft2) made up of basically 2 rooms. There have been some delays and the owner wants to move into one of the rooms while they finish the other. Provisions... Last reply: Susann Geithner, Feb 10, 2011, 12:06 pm |
|
International standards for Option 2, indoor air monitoring?CI-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by Reinhard Oppl on Jan 7, 2011, 2:14 pm
EQ credit 3.2, option 2, references to: Last reply: Tristan Roberts, Jan 9, 2011, 11:32 pm |
|
Mechanical floorsCI-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by Billy Ng on Nov 26, 2010, 10:29 am
I have a mechanical floor that is boxed in with no windows. this floor is just... Last reply: Scott DeGaro, Nov 26, 2010, 11:57 am |
|
Areas of questionCI-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by Elizabeth Repin on Jan 22, 2010, 6:20 pm
We have a food distribution warehouse. Would the 82,000 sq foot freezer need... Last reply: Shannon Gray , Apr 21, 2010, 4:32 pm |
|
Flush monitoring requirementsCI-2009 IEQc3.2: Construction IAQ management plan - before occupancyposted by Mary Davidge on Jan 20, 2010, 10:50 am
We have a project with two types of spaces, one is a naturally ventilated warehouse and the other is office with package units. At a local ashrae meeting the speaker stated that to achieve the... Last reply: Tristan Roberts, Jan 20, 2010, 8:02 pm |