When should I submit Construction credits?
posted by Mark Meaders on
I have a project in which the building substantial completion is Oct. 2016, but the final site work/ parking won't be completed until March 2018.
Substantial Completion, C of O, TCO
posted by Erika Duran on
Per the LEED certification Policy – we can submit construction review at Substantial Completion (defined as the date on which the building receives a Certificate of Occupancy or similar official in
Submitting a Product to meet LEED Certification
posted by Jeremy Henak on
Looking at what the process is for submitting a product for LEED certification. Thanks, Jeremy
preliminary design review - chiller - Baseline
posted by jana Paulech on
Hi, I would like you to ask for helping me with one LEED issue. We were doing energy model and we have received comments to our model, which one of them is this one: 8.
Appealing an EP
posted by Charles Nepps on
We had one of 3 EP's denied during our final review.
Review Team structure
posted by Charles Nepps on
I've always been curious how exactly the "Review Teams" are put together and function.
New to LEED Submitals
posted by Joel Clonch on
I have a mill-work submittal that requests : LEED Submittals: 1. Product Data showing VOC content does not exceed 30 g/L for wood adhesives and 80 g/L for contact adhesives. 2.
Guide missing from LEEDv3 credit library
posted by Raphael Sperry on
Has anyone else noticed that the Guide sections of the credit library are not available any more? What happened? They are still there for v4, but not for v3...
Adding credits after Construction Decision
posted by Deborah Lucking on
We just received Construction Decision and the client wants to know if we can submit additional credits (to get from LEED Silver to Gold). Has anyone tried this? Any advice? Thanks!
Prelim and Final Submission Timelines
posted by Amy Harmon on
What are the expected prelim and final submission timeline for both design and construction credits by USGBC?