Daylighting - Prescriptive Calc

NC-2009 IEQc8.1:Daylight and Views—Daylight
posted by  Francisco Villela  on 

Working on an Auto Dealership. Is it possible that I have too much window to qualify for Daylighting? All my calcs are resulting in VLT x WFR's well beyond 0.18. Any thoughts?

4
Sun Oct 23, 2011, 11:53 pm

Ground depth beneath vegetated area

NC-2009 SSc5.2:Site Development—Maximize Open Space
posted by  Valentin Grimaud  on 

Hi everyone! I have a very specific question regarding vegetated area.

3
Fri Oct 21, 2011, 10:38 pm

Performance Option and 10% Power Density Reduction

CI-2009 EAp2:Minimum Energy Performance
posted by  Luis Miguel Diazgranados  on 

Hi everyone I'm kind of confused because the explanation on the Bird's Eye View differs from the Credit Language's one.

2
CEO
Green Commons, LLC
LEEDuser Expert
586 thumbs up
Thu Oct 20, 2011, 4:25 pm

Free valet parking for LE/FEVs - Does this count?

NC-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehicles
posted by  Tricia Loe  on 

My question is similar to the most recent question. We are working on a hotel project with valet parking.

2
Vice President
WSP Built Ecology
LEEDuser Basic Member
42 thumbs up
Thu Oct 20, 2011, 3:52 pm

Enhanced Commissioning Action Steps

CI-2009 EAc2:Enhanced Commissioning
posted by  Garrett Billings  on 

We are afraid we will get denied out submittal for enhanced commissioning because we didn't follow the process step-by-step as defined above in the "Action Steps".

5
Default Avatar
Project Manager
Jones Lang LaSalle
LEEDuser Basic Member
18 thumbs up
Thu Oct 20, 2011, 3:47 pm

Anyone used 3ds max for Option 1?

NC-2009 IEQc8.1:Daylight and Views—Daylight
posted by  Erica Downs  on 

Has anyone had success using 3ds max for the Option 1 simulation? Thanks.

2
Director of Sustainability
DBR Engineering Consultants
LEEDuser Basic Member
244 thumbs up
Thu Oct 20, 2011, 2:07 pm

an update from February 2011

CI-2009 IEQc5:Indoor Chemical and Pollutant Source Control
posted by  Seonhee Kim  on 

This is the updated portion of IEQ c5. In mechanically ventilated buildings, each ventilations systems that supplies outdoor air shall comply with the following: o Particle filters or air cleanin

3
Director - Green Building Advisory
Colliers International Ltd.
LEEDuser Basic Member
201 thumbs up
Tue Oct 18, 2011, 10:38 pm

System status report for ventilation system

EBOM-2009 IEQp1:Minimum IAQ Performance
posted by  Sundararaj Subburaman  on 

We are pursuing LEED-EB:O&M for an office building. It has BAS functions for heating, ventilating, and air conditioning system.

2
Director of Operations
Transwestern Sustainability Services
LEEDuser Basic Member
355 thumbs up
Tue Oct 18, 2011, 5:54 pm

SSc6.1 Pond with Flow Restrictor and Total Stormwater Volume

NC-2009 SSc6.1:Stormwater Design—Quantity Control
posted by  Sandra Bauder  on 

I am having the same issue as Lucy (October 18, 2010) on one of our current projects, and the comments by Gregory and Jennifer were helpful but I still have some questions. Scenario: -existing impe

2
Principal
Emerald Built Environments
LEEDuser Basic Member
900 thumbs up
Mon Oct 17, 2011, 7:16 pm

EAp2- Energy Modelling and Process Loads

NC-2009 EAp2:Minimum Energy Performance
posted by  Marcio Alberto Casado Pereira  on 

Hi, I am working on a project (Stadium) where the only significative improvement on energy performance is lighting because the COP of the HVAC is basically the same and the envelope is not much

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Mon Oct 17, 2011, 4:50 pm