Line of Sight from Workstations

NC-2009 IEQc8.2:Daylight and views - views
posted by  Andrew Ellsworth  on 

I have two questions that may seem nitpicky, but are relevant to achieving this credit.

3
Default Avatar
Ellsworth Building Portfolio Services
LEEDuser Basic Member
3 thumbs up
Mon Aug 26, 2013, 1:22 pm

green house and daylighti credit

NC-2009 IEQc8.1:Daylight and views - daylight
posted by  Oleg Petryuchenko  on 

We have large warehouse project that also has a green house as a part of the building. could this area be excluded from daylighting?

4
Fri Aug 23, 2013, 10:14 pm

All Interior finishes qualify based on IEQ 4.1-4.4, still pursue

Pilot-Credits EQpc21:Low-emitting interiors
posted by  Trinidee Shelton  on 

If all interior finishes we have meet the requirements of IEQ 4.1-4.4, is it still possible to pursue this credit as well? Is it advisable in order to compare the two methods of review?

2
Founder & Community Director
Metricorps
LEEDuser Expert
7783 thumbs up
Fri Aug 23, 2013, 8:51 pm

Existing 1MW PV Array feeding new LEED Project on Campus

NC-2009 EAc2:On-site renewable energy
posted by  Greg Kight  on 

My project is a LEED v2.2 NC 32,000 sf project going for an 'individual' certification on a campus of existing buildings (None others are certfied or pursuing certification).

5
Fri Aug 23, 2013, 7:40 pm

VAV minimum for Ds

EBOM-2009 IEQp1:Minimum indoor air quality performance
posted by  George Kotsis  on 

Hello All: Is there any specific requirement from LEED for what the VAV minimum should be during cooling or heating?

3
Fri Aug 23, 2013, 4:42 pm

Major Renovations Project

NC-2009 SSc1:Site selection
posted by  VICTOR MORENO  on 

Hi, I am performing a Major Renovation Project that footprint building is equal to Project area site.

4
Founder & Community Director
Metricorps
LEEDuser Expert
7783 thumbs up
Fri Aug 23, 2013, 4:45 am

EA Cre 4_LEEDonline form

CS-2009 EAc4:Enhanced refrigerant management
posted by  Adam Targowski  on 

This credit is listed in Appendix 4 under case C so it should include tenant spaces as well. I have a question regarding filling in the LEEDonline form.

3
Mechanical Engineer
HKS
LEEDuser Basic Member
5 thumbs up
Thu Aug 22, 2013, 10:16 pm

System 6 or System 8?

NC-2009 EAp2:Minimum energy performance
posted by  Rob Watson  on 

Our building is 7 floors above ground with a conditioned basement and is about 70K ft2.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4461 thumbs up
Thu Aug 22, 2013, 8:16 pm

Housing Densities and FAR

ND-v2009 NPDp2:Compact development
posted by  Colin Day  on 

Hello Eliot, I am having a difficult time understanding the language of NPDp2.

2
LEED AP-ND, Principal
Criterion Planners
LEEDuser Expert
231 thumbs up
Wed Aug 21, 2013, 11:54 pm

VRP calculations for multi-family buildings

NC-2009 IEQp1:Minimum indoor air quality performance
posted by  Courtney Royal  on 

Hello, Our building is a multifamily building project and my question is, are we still required to complete the VRP calculations for this prerequisite?

5
Sr. Sustainability Consultant
Taitem Engineering
LEEDuser Basic Member
36 thumbs up
Wed Aug 21, 2013, 7:47 pm