Forum quick links
Lease Agreement an option to comply with the credit requirements
CS-2009 IEQc1:Outdoor Air Delivery Monitoringposted by Katherine Ann Resurreccion on
Hi, We are currently documenting the requirements for this credit and our option in order to comply is to provide a Tenant/Lease Agreement.
Process loads
NC-v4 EAc2:Optimize energy performanceposted by Ake Larsson on
In our company, we have introduced LEED as mandatory for all new construction projects.
How long do you have to do surveys?
NC-2009 IEQc7.2:Thermal Comfort—Verificationposted by Parker williams on
How long do you have to do surveys? Is this suppose to be ongoing forever?
EAp2-4: Energy Star equipment: conversion from kWa to Watts
CI-2009 EAp2:Minimum Energy Performanceposted by Sarah Simchuk on
I'm attempting to register the energy star equipment for my project under Table EAp2-4. The table asks for Rated Power in WATTS.
Rated power
CI-2009 EAp2:Minimum Energy Performanceposted by Yaser Al Sharif on
From where can i take rated power for equipments like laptop , i read it on laptop about 55wh then i divded it by work hours give me 6.7watt , is that right ??????
M&V approach case 2 (75% or more of total building area)
CI-2009 EAc3:Measurement and Verificationposted by Gaston Michaud on
We were trying to pursue this credit by developing and implementing a M&V plan following option C from the IPMVP, but after reading some comments, it seems that this path was removed.
Clarification
CI-2009 EAc3:Measurement and Verificationposted by Redy Truccolo on
Hi Marcus, We've a LEED CS certified building in which the Tenant will occupy almost 100% of the total area, so we will fall in CASE 2. We obtained the CS certification EAc5.2 credit and we've sub
Where to find the Ecologo-certified products?
EBOM-2009 IEQc3.3:Green Cleaning—Purchase of Sustainable Cleaning Products and Materialsposted by Helen Samuel on
Now that Ecologo was acquired by UL, where can I find which products are Ecologo-certified?
Molok Containers for MRp1
CS-2009 MRp1:Storage and Collection of Recyclablesposted by Kristopher Lashley on
We are looking to install a 5000L Molok recycling bin for a LEED 2009 CS building that will be a restaurant. According to the reference guide a 11.6m recycling area would be required.
EV Ready acceptable?
CS-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehiclesposted by Dylan Connelly on
For Core & Shell projects - is installing 3% of the parking stalls to be EV ready acceptable to achieve these points?