Mid-Rise-v4 EAp1:Minimum energy performanceposted by Sue Bryant on
The EAp1 v4 requirement is to meet ESv3 by completing the thermal enclosure system rater checklist, the HVAC system quality install rater and contractor checklist and the water management system bu
Lighting Power Density requirement for Tenant spaces
CS-2009 EAp2:Minimum Energy Performanceposted by Pedro Urazan on
Hi, Is it required that the Tenants comply in their lighting designs with the Lighting Power Density requirement of ASHRAE 90.1 2007?
WE_Cr1 "Outdoor Water Use Reduction": Installation of a well
NC-v4 WEc1:Outdoor water use reductionposted by Francesco Passerini on
Is it possible to install a well specifically to collect groundwater for irrigation to meet the intent of the credit to reduce potable water use for irrigation?
Model Calibration - Margins for Error
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Ciaran McCabe on
For a new office building would it be acceptable to use these error margins for an M&V Report.
Hotel Occupancy
NC-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehiclesposted by jupiter luner on
I've determined the occupancy for a hotel project we are working on based upon LEED interpretation 2706606.
Hotel Recycling Note
NC-2009 MRp1:Storage and Collection of Recyclablesposted by jupiter luner on
On a hotel project we are trying to avoid putting two bins within the rooms.
Onsite solar PV generation - 10 years contract
EBOM-v4 EAc7:Renewable energy and carbon offsetsposted by Ameet AA on
Hi, Is it compulsory to sign a 10 years contract with the solar PV supplier (the PV panels are installed on the rooftop of the project building)?
GREEN POWER - WIND Mills
NC-2009 EAc6:Green powerposted by SAMY Chamy on
Dear Concern:- Our client produce huge amount of Renewable energy by wind mills and the energy produced via wind mill is almost 5 times greater than LEED project annual energy consumption so pl
WEp1 Form V01
NC-2009 WEp1:Water Use Reduction—20% Reductionposted by Melissa Merryweather on
Hi, I have form V01 for WEp1, and I can't find any information to say that this form has been updated (V01 is the only one listed on USGBC forms source), but there was a reference somewhere to an u
Water Pressure to Fixtures
CS-v4 WEp2:Indoor water use reductionposted by Ciaran McCabe on
Is it an absolute requirement that the proposed pressure (in PSI) matches the baseline. Can we use a flow rate at a lower pressure to avoid excessive pump sizes ?