Vegetation under solar panels
NC-2009 SSc5.1:Site Development—Protect or Restore Habitatposted by Cesar Ruiz on
Hello, We are working on a project which is going to have almost all of its roof covered by solar panels.
A partial ceiling area was affected by mold
Schools-2009 IEQc10:Mold Preventionposted by dia2000@gmail.com dia2000@gmail.com on
Hello, Our project is a LEED NC v2009. Due to a heavy rain season, it happened that some leakage lead to a partial grow of mold in some ceiling areas which are made from gypsum boards.
Adsorption Heat Pump
Homes-v4 EAc10:Space heating and cooling equipmentposted by FABIO VIERO on
Hello everyone, in case of Gas Adsorption Heat Pump, which is the reference system we should consider for checking credit compliance? Thanks.
1-floor renovation in an 2009 EBOM Certified Building
EBOM-2009 EAp2:Minimum Energy Efficiency Performanceposted by John Krutko on
I am proposing on a project in which the scope is the renovation of a single floor of a 10 story building that is currently LEED 2009 EBOM certified.
Energy Modelling - Australia
NC-v4 EAp2:Minimum energy performanceposted by Quentin Jackson on
We have a Green Building Council in Australia that has a very advanced energy simulation methodology that achieves the same outcomes as the ASHRAE 90.1 process outlined in LEED.
>10% exemption possible?
EBOM-2009 MPR2:Must be a complete, permanent building or spaceposted by Rasita Masalskyte on
Hello, Has anyone heard of possibility to exclude >10% of building gross area that is under separate ownership and management? In our case such space makes 14%.
Project size extended in the middle of construction
NC-v4 MPR3:Must comply with project size requirementsposted by wachira sosaeng on
My project registered for LEED 2009, mixed use building with 2 towers on the same podium.
Process Water
Retail-NC-v2009 WEp1:Water use reductionposted by Donald Green on
We have a project where there are a couple pieces of equipment that may be considered Process Water: a mobile pressure washer and a parts washer.
Project size extended in the middle of construction
NC-2009 MPR4:Must comply with minimum floor area requirementsposted by wachira sosaeng on
My project registered for LEED 2009, mixed use building with 2 towers on the same podium.
Demolished and rebuilt envelope
NC-v4 EAp2:Minimum energy performanceposted by Francesco Passerini on
If the envelope is demolished and then rebuilt with the same shape does Table G3.1 part 5., baseline, point f apply?