Baseline Heating Type with Campus Steam Humidification

NC-v4 EAp2:Minimum energy performance
posted by  Michael Hill  on 

I am modeling a lab builidng for LEED v4 and I am trying to determine what the Baseline heating type should be.

1
Tue Feb 13, 2024, 7:54 pm

Walk-in coolers and freezers

NC-2009 EAp2:Minimum Energy Performance
posted by  Vernon Smith  on 

I am modeling a 35,000 sf cafeteria that has seven walk-in coolers/freezers with total floor area of about 1700 sf. They are in the basement and first floor of the building.

5
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Tue Feb 13, 2024, 3:20 pm

Projects with several distinct structures

Hospitality-NC-v4 MPR3:Must comply with project size requirements
posted by  Manzil Shrestha  on 

"Any single structure that is larger than 25,000 square feet (2 320 square meters) must be registered as a separate

0

Turf Grass

NC-v4 SSc3:Open space
posted by  Vaneeza Javed  on 

Is Normal grass consider in Turf Grass or not?

1
Wed Jun 5, 2024, 7:41 am

Open Space and Turf Grass

NC-v4 SSc3:Open space
posted by  Vaneeza Javed  on 

What does leed implies when it mentions Turf grass and why Turf grass does not count as vegetated area?

1
Wed Jun 5, 2024, 7:44 am

Thermal compliance of Revolving doors

NC-v4 EAp2:Minimum energy performance
posted by  Alokmay Behera  on 

I am working on a LEED project with revolving doors at the building entrances. The project has a proposed glazing specification.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Wed Feb 7, 2024, 11:42 am

Purchasing - Lamps with UV-C

NC-v4 INc1:Innovation
posted by     on 

Does anyone know if the Purchasing - Lamps innovation credit requires reporting of UV-C lights in air handlers (for coil irradiation and virus mitigation)?

2
Practice Leader - Sustainability
EUA
LEEDuser Expert
510 thumbs up
Mon Feb 5, 2024, 8:11 pm

Concern regarding entryway systems

EBOM-v4.1 EQc1:Green Cleaning
posted by  Wafa Arif  on 

Hello,

Under option 2 - Entryway systems, we need to put in place 10 feet elements in the primary direction of travel.

4
Managing Partner
Ecoimpact Consulting
LEEDuser Expert
171 thumbs up
Mon Feb 5, 2024, 6:33 pm