How to define the "project's energy-related systems"?
CI-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Andrew Gil on
I am seeking clarity on this point given the GCBI's June 2011 update of MPRs and the current emphasis on defining a project "in it's entirety".
Commissioning Services Contracted Through Design Firm?
CI-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Jaclyn Whitaker on
We've just received an RFP for a new project instructing my firm to provide fees for LEED Administration, Energy Modeling and Commissioning.
COMMISSIONING
CI-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Yaser Al Sharif on
WE ARE WORKING ON LEED CERTIFICATE FOR CI BUILDING (14000 SQUARE FOOT) THE POINT IS, WE HAD RENTED OFFICE AND THE HVAC SYSTEM WERE INSTALLED SINCE FIVE YEARS AGO, NEWLY WE INSTALLED NEW HVAC EQUIPM
Chiller
CI-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Saju Varghese on
Does a chiller have to be considered in commisioning even if the chiller is serving other tenants as well?
Latest a CxA can be brought into project
CI-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Judy Peterson on
My client was late in committing to LEED for an interior renovation, so is this prerequisite achievable if commissioning was not incorporated into the project until the construction phase?
Fundamental Commissioning vs Enhanced Commissioning
CI-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Zeb Foss on
Hello, I am in Canada so we are sill required to use LEED CI 1.0, and I have a question regarding the responsibilities of the CxAs.
Commissioning for LEED-CI
CI-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by monu goyal on
We are going to commission our interior space to get certify with LEED-CI.
Cx requirements for small office remodel
CI-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Tara Messa on
I am working on a project that is a relatively small office remodel seeking LEED certification.
Scope of system performance testing
CI-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Billy Condor on
I have two questions regarding Cx activities for a LEED CI proyect: 1.