Calculation of replacement cost
NC-2009 MRc3:Materials Reuseposted by Adrienn Gelesz on
Hi, When there is some material that was donated, that actually does not appear in the total material cost (no money actually spent).
How can I calculate Materials and Resources by Default materials cost
NC-2009 MRc3:Materials Reuseposted by mohamed nur hashi on
I am a student and I am working on leed material calculation.
MRc3 and reused furniture
NC-2009 MRc3:Materials Reuseposted by Jeff Wiedmeyer on
My client wants to know what credits might be applicable to the re-use of furniture from another one of its projects for use in the current project. I told the client that I believe the only
Reusing existing concrete slabs
NC-2009 MRc3:Materials Reuseposted by Laura Rebbe on
We are maintaining an existing aircraft hangar floor slab and an adjacent concrete apron for reuse as an equipment parking area.
Receipt Proof Requirements
NC-2009 MRc3:Materials Reuseposted by jupiter luner on
I wanted to clarify something that I recently heard from a contractor on a LEED project.
Trees on site to be used for furniture, blocking and/or veneer.
NC-2009 MRc3:Materials Reuseposted by Seonhee Kim on
If some of trees on site need to be cleared and we decide to use it for furniture, blocking and/or veneer, does this count as MRc3?
Demolished Building - Material Reuse
NC-2009 MRc3:Materials Reuseposted by Lauren Bellamy on
Our client has demolished the existing structures on our site and salvaged all the cladding and flooring materials (i.e.
Material Reuse
NC-2009 MRc3:Materials Reuseposted by Scott Gharda on
I am working on a project where we will be renovating an existing 2 story warehouse to turn it into office space.
Cost to be Excluded in the total proj material costs for MR CR3
NC-2009 MRc3:Materials Reuseposted by Benjie Herrera on
I just want to inquire if we will include HVAC equipment, PV arrays, Solar hotwater collectors, generator, fire alarm control panels, etc.
Salvaged granite block
NC-2009 MRc3:Materials Reuseposted by Sara Sweeney on
Hi I am working on a project where 83.75 tons of granite slabs were removed from a site during site clean-up for the new bilding being built.