Forum quick links
Wood Palettes
NC-2009 MRc2:Construction Waste Managementposted by Samantha De Leuw on
On my project, the subcontractors are responsible for reusing wood palettes and, if applicable, selling them back to the manufacturer. Is there a way to record this?
Asphalt Roll Roof Recycling
NC-2009 MRc2:Construction Waste Managementposted by Sabrina B on
I am working on a existing building renovation. The existing roof, which will be demo'd, is asphalt roll with batt insulation underneath.
Exemplary Performance - forms question
NC-2009 MRc2:Construction Waste Managementposted by André Knutsson on
We have finished the project whith a 97.2 % recycling, and are pursuing the one Innovation in Design credit. When we register the IDc1.1 we do not get to choose the MRc2 in the dropdown window.
landfill has a recycle/reuses program in place
NC-2009 MRc2:Construction Waste Managementposted by ming zeng on
We have a project that the local landfill has a recycle/reuse program. For example, they will chip out wood and reuse it as road bed materials to build the road system in the landfile.
Construction Waste Management || Clean Fill
NC-2009 MRc2:Construction Waste Managementposted by Andrew Gil on
Apologies if this topic has already been addressed (and, on that note, I have a suggestion: As the number of postings grows & grows, it might be very helpful to be able to search within a topic
Tracking / documenting items being reused from demo'd bldg
NC-2009 MRc2:Construction Waste Managementposted by Renee Shirey on
On our site we have several items that will be salvaged from our demo'd building/site (furniture, playground equipment) that will be used with the new building/site.
Construction Waste Theft!
NC-2009 MRc2:Construction Waste Managementposted by Jeffrey Westall on
We are having a serious issue with all of our metal scrap being stollen from the jobsite dumpster. This has impacted our percentage for recycling dramatically. We are currently at only 28%.
Trees
NC-2009 MRc2:Construction Waste Managementposted by Norma Lehman on
We are removing a lot of trees on our construction site, if we turn it into mulch does this qualify toward our CWM credit? or would it be material reuse? thanks for your help!
Guidelines on Construction waste Handling
NC-2009 MRc2:Construction Waste Managementposted by Amgad Khattab on
Hi, I’m currently working on a LEED project in Egypt. Waste handling is a new subject for us and I need some guidelines on the following: 1.
Hazardous Waste
NC-2009 MRc2:Construction Waste Managementposted by Veronika Sundberg on
Hi, I’m currently working on a LEED project in Sweden. In overall we are very good at waste handling, but I think that we include different fractions in hazardous waste.