We have a project that the local landfill has a recycle/reuse program. For example, they will chip out wood and reuse it as road bed materials to build the road system in the landfile. Ourcontractor will dump construction debri-wood to this landfill. Are we qualified for the credit? If the cost of dumping at this landfill is higher than at other landfill that doesn't have a recycle/reuse program, does this make difference for applying to this credit? If the contractor sort out wood from other construction debri, does it make difference? Thanks.