Planned/future Photovolatic installation

NC-2009 EAc2:On-Site Renewable Energy
posted by  Stacey Olson  on 

I'm working on a project that has installed the infrastructure to support a PV array, and is pursuing Enhanced Commissioning.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Wed Aug 31, 2016, 4:37 pm

RE: LI#10397

NC-2009 EAc2:On-Site Renewable Energy
posted by  Joe Manganelli  on 

Hi All, Does anyone have any experience with LI#10397? This LI# stipulates an alternative compliance path for facilities that have 60% or more non-regulated loads. QUESTION 1: I cannot find any

3
Default Avatar
architect, human factors consultant
Fluor, Kent State University, xplr design, llc
LEEDuser Basic Member
1 thumbs up
Wed Aug 17, 2016, 8:31 pm

RE: Feeding renewable energy into the project

NC-2009 EAc2:On-Site Renewable Energy
posted by  Joe Manganelli  on 

Hi All, We have a campus with a substation on-site (on owner's property) that will be owned by the local utility.

3
Default Avatar
architect, human factors consultant
Fluor, Kent State University, xplr design, llc
LEEDuser Basic Member
1 thumbs up
Wed Aug 17, 2016, 3:35 pm

PV Energy sent to Local Grid - Eligibility for EA c1 & EA c2

NC-2009 EAc2:On-Site Renewable Energy
posted by  varun potbhare  on 

I am working on Museum Project in Doha. Owner of the Museum intends to install 3000 panels on the car park.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Mon Aug 15, 2016, 5:38 am

Form

NC-2009 EAc2:On-Site Renewable Energy
posted by  GISELA FARHAT DE ARAUJO  on 

The EAC2 Form asks for "Annual Renewable Energy Cost". You said in a post that is "It is the avoided energy cost associated with the renewables at the virtual rate from the Proposed model.

5
Wed Jul 13, 2016, 2:41 pm

Eac2 form

NC-2009 EAc2:On-Site Renewable Energy
posted by  GISELA FARHAT DE ARAUJO  on 

Hi. I have a 34,2 Kw solar system that generate 49.425 kWh/year. I need help to fill the form: 1- In table: Renewable energy - what information should I put in the item "Annual Energy Cost"?

4
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Wed Jul 13, 2016, 10:56 am

Shared solar array on a campus with separate utility feeds

NC-2009 EAc2:On-Site Renewable Energy
posted by  Rebecca Bryant  on 

We are working on a hospitality project that is attempting LEED Gold, and is part of a larger campus.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Tue Jul 12, 2016, 6:42 pm
2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Fri Jul 1, 2016, 7:44 pm

Solar energy used with previous LEED project credit

NC-2009 EAc2:On-Site Renewable Energy
posted by  Zane Lichtneger  on 

We have a solar farm on our site that generates about 1.7 million kWh of electricity per year. The array is 100% grid tied selling all energy back to the public utility.

3
Default Avatar
Sustainability Analyst
SAS Institute Inc.
LEEDuser Premium Member
5 thumbs up
Fri Jun 24, 2016, 4:11 pm

Solar Water Heating System

NC-2009 EAc2:On-Site Renewable Energy
posted by  Kalyan Nishtala  on 

Hi, Has anyone found a reliable calculator for estimating savings from a solar water heating system that has been submitted and accepted by USGBC reviewers.

4
Head of Energy & Environmental Management
EB Project Management | Green Building Consultants
LEEDuser Basic Member
14 thumbs up
Fri Jun 17, 2016, 1:06 pm