ASHRAE 90.1-2007: Minimum Efficiency Requirements (Heat pump)

NC-2009 EAp2:Minimum Energy Performance
posted by  Jorge Mato Rial  on 

Hello Everyone: I am working in an office building project located in Galicia (Spain). We are carrying out the selection process of the heat pump for the air conditioning of the building.

7
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Wed Jul 5, 2017, 6:53 am

Exterior lighting not yet designed

NC-2009 EAp2:Minimum Energy Performance
posted by  Vassil Vassilev  on 

Greetings, The project we are modeling at the moment is supposed to have exterior lighting for the facades, some parking lots and some walkways. The exact LPD however is still to be calculated and

4
Tue Jun 27, 2017, 2:23 pm

Baseline Garage Ventilation

NC-2009 EAp2:Minimum Energy Performance
posted by  Vassil Vassilev  on 

Greetings, In our project (registered as per LEEDv2009) there are several garage ventilations. According to ASHRAE 62.1-2007, the garage exhaust rate is to be sized to 0.75 cfm/ sq.ft.

3
Mon Jun 26, 2017, 6:43 pm

Energy Rates for CHP used Project

NC-2009 EAp2:Minimum Energy Performance
posted by  SAMY Chamy  on 

Dear All Our Project have CHP (2 CNG Generator 500Kw with VAM Chillier 100TR) what is rate we use for BASE Case and Design Case For Design case we use the Fuel(CNG) cost invested to run a Gener

5
Mon Jun 26, 2017, 1:24 pm

Baseline Hot water pump power for Purchased heat

NC-2009 EAp2:Minimum Energy Performance
posted by  Vassil Vassilev  on 

Greetings, The project we are modeling follows LEDD v3 - 2007 (System 7) and the heating source is purchased heat. There are two question related to this issue. 1.

3
Default Avatar
Vice President / Principal
2rw Consultants, Inc.
LEEDuser Basic Member
1 thumbs up
Wed Jun 21, 2017, 7:54 pm

Baseline Chiller plant - System7

NC-2009 EAp2:Minimum Energy Performance
posted by  Vassil Vassilev  on 

Greetings, Could you please provide some advice to the following case (the building belongs to System 7): 1.

5
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Tue May 30, 2017, 12:47 pm

Glass in Jalousie-style

NC-2009 EAp2:Minimum Energy Performance
posted by  James Lee  on 

Hi, Is there specially I have to concern when I define the fenestration's properties for jalousie-style glass in energy modeling? Thanks in advance

7
Wed May 24, 2017, 6:01 pm

Alternative to Table 1.4

NC-2009 EAp2:Minimum Energy Performance
posted by  Ben Cullum   on 

When submitting energy models to NYC we have to fill out a form called an EN-1 that is very similar to Table 1.4 and provides the same information. Can we provide the EN-1 in place of Table 1.4?

3
Wed May 17, 2017, 12:53 pm

Lagre building modeling suggestion

NC-2009 EAp2:Minimum Energy Performance
posted by  Vassil Vassilev  on 

Greetings, The project we are modeling is a huge one - a little more than 900 000 sq ft and it is not C&S.

3
Thu May 11, 2017, 6:41 pm

basecase System

NC-2009 EAp2:Minimum Energy Performance
posted by  SAMY Chamy  on 

Dear Concern:- Greetings Our project is G+5 but A/c spaces are located in 3 Floors only and A/c area is totally below 10000 Square feet only (electrical heating only) so we have some queries in

5
Enginneer
T&T Green
LEEDuser Basic Member
9 thumbs up
Thu May 11, 2017, 7:06 am