FAQs about EAp2 :

Can the Passive House Planning Package (PHPP) be used to energy model for LEED?

Is it acceptable to model a split-type AC with inverter technology compressor as a heat pump, like modeling VRF?

Can the Trace 700 'LEED Energy Performance Summary Report' by uploaded to LEED Online in lieu of the Section 1.4 tables spreadsheet?

A portion of our building envelope is historic. Can we exclude it from our model?

Which baseline HVAC system do I use if my building has no heating or air conditioning?

For an existing building, do I need to rotate the model?

Our project has a diesel backup generator. Should we include it in our energy model?

Our project has a large process load—75%. Despite our efforts to make an efficient HVAC design, the cost savings are minimal. What can we do to earn this prerequisite and be eligible for LEED certification? Is there any flexibility in how we model the p

Can SHGC be higher in the proposed than in the baseline model?

Our process load is higher than 25%. Do we have to justify that?

Do I need to justify the electrical and fuel rates I am using in my model?

Our local code references ASHRAE 90.1-2010. Should I use that for my documentation, or 90.1-2007?

Can I claim exterior lighting savings for canopy lighting even though a baseline model cannot include shading elements?

The project is built on a site with existing exterior lighting installed. How should this be accounted for?

Can mezzanines open to floors below be excluded from the energy model?

How do I provide a zip code for an international location?

For a project outside the U.S., how do I determine the climate zone?

For a project outside the U.S., how do I determine the Target Finder score?

Do hotel rooms need automatic light shut-off control?

How commonly are the 90.1 mandatory compliance forms submitted as part of EAp2/EAc1?

View answers »

Forum discussion

NC-2009 EAp2:Minimum Energy Performance

Energy Rates for CHP used Project

Dear All Our Project have CHP (2 CNG Generator 500Kw with VAM Chillier 100TR) what is rate we use for BASE Case and Design Case For Design case we use the Fuel(CNG) cost invested to run a Generator to create Electricity Which rate can we use for Base case as per LEED Reference guide the Back up energy or Electricity cost may be considered as base case cost but I have a doubt in that base case cost arriving 1.we use diesel generator for Electricity back up can we arrive the electrical cost consumption using the specific fuel consumption from catalogue But the cost of electricity is varying for both a cases because of the Specific fuel consumption of CNG Generator, Diesel Generator. Can we take this advantage IN energy Simulation As per this energy rates variation we get 20 - 25% saving can we claim this saving as a benefit of CHP. is it acceptable manner

1

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Mon, 02/01/2016 - 04:33

Awaiting for your reply

Mon, 02/01/2016 - 18:39

The rate used for the CHP in the proposed must be identical to the rate used in the baseline. You can't use the diesel rate for the baseline.

Sat, 06/24/2017 - 10:41

I am working on a project where the same scenario exist as mentioned above with natural gas generator for power generation where heat is recovered to run the VAM chiller. So, i modeled the generator and VAM chiller as CHP in the proposed design. Here the backup source is electricity from grid. so is it acceptable to model the baseline design with energy rate of grid sourced electricity? Kindly clarify. Thanks in advance.

Mon, 06/26/2017 - 13:24

Sounds right to me.