Commissioning using generator
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Omar Elrawy on
Dear all, I have a case where project team suggests running all Cx activities on the building's emergency generator, in addition to an external generator.
Chiller
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Saju Varghese on
Should the chiller be considered part of the commisioning and M&V metering even if it's serving other tenants as well?
Pending Systems for Commissioning
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Shabari Shaily Gerber on
Hi We are currently busy with LEED documentation of a manufacturing facility that is under operation for a year now.
Contract through Design Team - conflicting information
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Rory Cousino on
I am going to ask a question that is probably been answered before - but I cannot find the simple answer. Can the CXA be contracted through / to the Design Team?
The overlap activities between CxA and CM Consultant
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Panupant Phapant on
Hi Can anyone share the CxA practice for LEED project in USA or other countries as we see that there are the overlap activities between the construction management consultant and CxA for LEED proje
Campus PV dedicated - not connected - to building requires Cx?
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Joyce Kelly on
A portion of a nearby, existing campus PV system has been dedicated - not connected - to our building.
commissioning of outbildings
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Jutta Berns on
we have a campus project where currently only the main building is undergoing certification.
Two Commissioning Agency
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Steve Valev on
We are documenting a project where a roof-mounted PV system was installed after the building was occupied and the original commissioning process was complete.
Re-commisioning
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by John Wood on
I am a PE who has been approached by a building owner with a request to have the building "re-commissioned." I have designed LEED projects before, and participated in the original commissioning, b
Cx Authority
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Giuseppe Medeghini on
LEED manual states that: "The commissioning agent must demonstrate experience on two prior projects." the two project have to be LEED certified or they can be even no certified but with similar siz