Should the chiller be considered part of the commisioning and M&V metering even if it's serving other tenants as well?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium forForum discussion
NC-2009 EAp1: Fundamental Commissioning of Building Energy Systems
Should the chiller be considered part of the commisioning and M&V metering even if it's serving other tenants as well?
LEEDuser is supported by our premium members, not by advertisers.
Go premium forTo post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.
Scott Bowman
LEED FellowIntegrated Design + Energy Advisors, LLC
LEEDuser Expert
519 thumbs up
May 1, 2013 - 10:50 am
The quick, but probably unsatisfactory answer, would be “yes”. All energy using systems should be commissioned that serve the building, but there are some other aspects if dealing with a District Energy System (DES), but even that has some requirements.
To give better guidance, I would need a little more information. You mention “tenants”, does that mean you are doing a core and shell project, or is the chiller plant in your building feeding other buildings? Is the plant existing or being installed with your project?
The metering is a whole different question, and again depends on how it is being fed. If part of a DES, then the metering would likely be a Btu meter for water used by your part of the project. Again, just do not have enough information to give you much more information.