Healthcare vs NC - Fundamental Commissioning
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Saju Varghese on
Hello, I'm looking into the difference between Healthcare and New Construction Fundamental Commissioning for a project but I have not been able to find anything related to that.
Approach for documentation with 2 Commissioning Agents
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Aishwarya Balagopal on
The project is registered as a Campus project with a Master Site including 4 new buildings, an underground parking structure, and landscape improvements.
Criteria of choosing CxA
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Patana Rattananavathong on
There are about 3 CxA sent me their proposals. This is my first project and I wonder that are their any criteria for choosing CxA.
Hotel
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Nelina Loiselle on
To satisfy the LEED requirements, does every room in a hotel have to be commissioned?
Do you submit form during Design or Construction Review phase?
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Nicole Kimoto on
For the EAp1 form, I'm confused as to whether I am supposed to fill out this form for the design preliminary review, because this is a Construction credit? Can someone please clarify?
Required Number of Construction Inspections?
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Benjamin Tressler on
Does LEED specify a required number of commissioning inspections during construction? We are trying to develop a scope based on the minimum requirements of LEED.
OPR Never Produced
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Ed Clark on
I was added to the project after construction due to staffing changes. An OPR was never produced. The design meets and exceeds the owner's goals and commissioning has been completed.