Values for Option 01 Calculation
NC-2009 WEc1:Water Efficient Landscapingposted by N Reifenstein on
We are trying to perform the calculation per the online credit form and are not able to access the ks, kd, and kmc values, which are supposed to be in the LEED v 2009 Reference Guide.
Future Municipal Greywater System Near SIte WEc1
NC-2009 WEc1:Water Efficient Landscapingposted by MANNY IGLESIA on
There is a fully funded Recycled Water Distribution System that is due to start by mid this year until the third quarter of 2021.
100 % Non potable power - No Compliance
NC-2009 WEc1:Water Efficient Landscapingposted by SAMY Chamy on
Dear All:-
Our project is use 100 % recycled water for irrigation (ETP Treated water) and so it is option 2 - path 1 and we have met the
Documenting Controller Efficiency
NC-2009 WEc1:Water Efficient Landscapingposted by Michael Hill on
In order to document controller efficiency will it be necessary for the landscape architect to calculate it or would it be acceptable to provide case studies such as those found at http://www.rainb
Existing grassland habitat within LEED boundary
NC-2009 WEc1:Water Efficient Landscapingposted by Lisa Meniketti on
If within our LEED site boundary we have a large portion of existing grassy land areas to remain as they are, as (SS1 and/or SS2) protected habitat, and we do not add irrigation to these grass
Vertical Garden
NC-2009 WEc1:Water Efficient Landscapingposted by Charalampos Giannikopoulos on
Please clarify whether a project needs to have vegetated space at a minimum of 5% of the site area. If yes, will vertical gardens count to this area in order to exceed the minimum 5% requirement?
NC-2009 WEc1 - Water Efficient Landscaping
NC-2009 WEc1:Water Efficient Landscapingposted by ayda nezhad on
Hi,
When we calculate the total irrigation design case(L) , is this volume per month or per day?
Clarification on Option 01 50% Saving - WEc1 - Water Efficient Landscaping
NC-2009 WEc1:Water Efficient Landscapingposted by SAMY Chamy on
Dear all :-
we are working in a project with 100% non potable water (On site recycling water 0 using for both Flushing fixture and Irrigation)