Planned Transfer Center
NC-2009 SSc4.1:Alternative Transportation—Public Transportation Accessposted by Josh Mauldin on
My project is a fire station that is the first project on the site of a mixed use development. A bus transfer center is planned to be built directly across from the fire station.
Proximity to rail station
NC-2009 SSc4.1:Alternative Transportation—Public Transportation Accessposted by Sheryl Swartzle on
Our one and only bus, which stops right outside our project entrance, is a 10 minute drive in heavy traffic (meaning many rides would be less than 10 minutes) but 3.5 miles to a Metro Rail station.
Existing bus stop
NC-2009 SSc4.1:Alternative Transportation—Public Transportation Accessposted by lance mccardle on
We are doing a major renovation on a multifamily housing complex that was built in 1990 with bike racks and a bus stop that the owners put in when the building was first constructed.
Project is in itself a public transportation system
NC-2009 SSc4.1:Alternative Transportation—Public Transportation Accessposted by Valentin Grimaud on
Hi, The project I'm currently looking at is a subway line, with the possible certification of each station independently. Could we consider that each station fills the requirements for this projec
Using BD+C SSc4.1 as an EBOM IO credit
NC-2009 SSc4.1:Alternative Transportation—Public Transportation Accessposted by Michael Smithing on
We're working on the EBOM certification of a building with excellent public transportation. Has anyone attempted to use SSc4.1 as an IO credit in EBOM?
200 rides per day required for shuttle buses?
NC-2009 SSc4.1:Alternative Transportation—Public Transportation Accessposted by Weidong Luo on
Private shuttles are employed to satisfy SSc4.1 on our project.
LEED Pilot Credit 30
NC-2009 SSc4.1:Alternative Transportation—Public Transportation Accessposted by S. Sachs on
We are pursuing v2009 certification on an office building for this credit using Pilot Credit 30 for bicycle routes (alternative compliance path); however, since this project started the pilot credi
Bus Line Rerouting for Adjacent Bridge Construction
NC-2009 SSc4.1:Alternative Transportation—Public Transportation Accessposted by Kevin McNulty on
Hi. My firm is working on a building that will be located right at the foot of a large bridge project that is currently in construction (estimated reopening in a few years).
Accessible Bus Stop
NC-2009 SSc4.1:Alternative Transportation—Public Transportation Accessposted by Brett Beckemeyer on
Our project has several bus stops within the 1/4 mile radius, and what I would consider to be the most direct route along the street to the stops is also within 1/4 mile walking distance.
SSc4.1
NC-2009 SSc4.1:Alternative Transportation—Public Transportation Accessposted by Magda Aghababyan on
We have campus project from building entrance to the 1st bus stop near about 520m. Is it possible to apply this credit.