Semi-permanent streams

NC-2009 SSp1:Construction Activity Pollution Prevention
posted by  Paula Hernandez  on 

Our project has a very small semi-permanent stream runing through it (i.e., the streams forms only in heavy rainfalls). .

2
Regional Stormwater Leader
Arcadis North America
LEEDuser Expert
144 thumbs up
Tue Apr 7, 2015, 10:29 pm

Perimeter Controls

NC-2009 SSp1:Construction Activity Pollution Prevention
posted by  Gabriela Mesquita  on 

Good day I want to consult in relation to a project in a lot of 10 hectares (about 25 acres) with a perimeter of 1377 m (about 4500 ft).

6
Wed Jan 14, 2015, 7:23 pm

LEED Boundary / Silt Fencing

NC-2009 SSp1:Construction Activity Pollution Prevention
posted by  Carrie Laurendine  on 

Currently working on a project that is a large site with an existing building currently on the site.

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Wed Jan 14, 2015, 6:04 pm

Checking ESC plan at design stage?

NC-2009 SSp1:Construction Activity Pollution Prevention
posted by  Hrvoje Kvasnicka  on 

Hi All Since this is a prerequisite which forms part of construction stage submittal, I was wondering if it there is a way to have the ESC plan reviewed by GBCI at design stage.

5
Wed Dec 31, 2014, 8:03 am

Zero lot line existing building renovation

NC-2009 SSp1:Construction Activity Pollution Prevention
posted by  Kim Shinn  on 

This project is a re-skin, and interior re-fit. Complete preservation of the structure. There was no site soil distrubance. What is required for SSp1 documentation?

4
Default Avatar
LEEDuser Basic Member
0 thumbs up
Fri Oct 17, 2014, 4:19 pm

Sediment Basin

NC-2009 SSp1:Construction Activity Pollution Prevention
posted by  Paula Hernandez  on 

Hello again, we are working on a project for which we are installing a sediment basin. According to EPA we could use the calculation of 3600 ft3 / acre drained to size it.

2
Regional Stormwater Leader
Arcadis North America
LEEDuser Expert
144 thumbs up
Thu Oct 16, 2014, 3:17 pm

In which construction phase can I certify my building?

NC-2009 SSp1:Construction Activity Pollution Prevention
posted by  Hazem Yusuf  on 

Construction phase of an office building is consisting of multi stages.

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Wed Oct 15, 2014, 8:25 am

Concrete Washout

NC-2009 SSp1:Construction Activity Pollution Prevention
posted by  Paula Hernandez  on 

Hello everyone, we are working on a project in an estate, part of this estate is the current LEED project, with its own LEED boundary.

2
Regional Stormwater Leader
Arcadis North America
LEEDuser Expert
144 thumbs up
Mon Oct 6, 2014, 12:00 pm

Dust control

NC-2009 SSp1:Construction Activity Pollution Prevention
posted by  Lawrence Lile  on 

What are the common measures used for dust control? SWPP plans I see around here always deal with soil erosion, but dust control is commonly ignored by inspectors and on most construction sites.

2
Regional Stormwater Leader
Arcadis North America
LEEDuser Expert
144 thumbs up
Mon Jul 28, 2014, 6:47 pm

Site Boundary, SWPPP and Erosion Control

NC-2009 SSp1:Construction Activity Pollution Prevention
posted by  Sandra Ehle  on 

My firm has built an Athletic Field house for a local school district. SWPPP and ESC plans were created and followed accordingly. Now here is where it gets complicated.