NC-2009 PIf2:Project Summary Detailsposted by Mike D on
A potential CI project has a core in the middle of the space, which is not part of the project but belongs to the landlord. No work will be done there.
Gross Square Footage
NC-2009 PIf2:Project Summary Detailsposted by Indochine Engineering VN on
Hi! My project is using double glazing facade, there is inner glass at the floor, then big air gap and the outer glass that is hang by a steel structure.
Hardscape
NC-2009 PIf2:Project Summary Detailsposted by Chris DeVolder on
Hi all, Thanks for the comments/feedback above. We have a small playing field/recreation field within our boundary adjacent to our building.
Crawl space included in GSF? Interior courtyards?
NC-2009 PIf2:Project Summary Detailsposted by Michael Wironen on
We have a fairly complicated building project that includes two areas that are unclear to me as to whether they should be included in the gross floor area calculation: 1.
10% exclusion of square footage "defined" for EBOM credits
NC-2009 PIf2:Project Summary Detailsposted by Wendy Parker, LEED AP on
Does the 10% excluded square footage for one credit (allowed in EBOM 2009) have to be the same excluded square footage used in another credit?
PIf2
NC-2009 PIf2:Project Summary Detailsposted by shaun Andriano on
This might be an easy one... Our PI form 2 was recently not approved following final design review.
Floor Area Ratio Calculation
NC-2009 PIf2:Project Summary Detailsposted by James Wieben on
The property my project is being built upon is 25,920 SF and my LEED Project Boundry contains 31,348 SF.
Plf's for a Master Site
NC-2009 PIf2:Project Summary Detailsposted by Donald Green on
A Master Site only needs to fill out Plf1 under the New LEED Platform as only that Plf shows up as possible in the scorecard. As LEED Online v3 does not have this capability, does a Master Site ha
PIf2- Project Summary Details
NC-2009 PIf2:Project Summary Detailsposted by Karly Michalowski on
What to do if project owner will not supply project budget?
Parking and Landscape
NC-2009 PIf2:Project Summary Detailsposted by SAMY Chamy on
Dear All:- Our Project is G+5 Factory Building compare to other floors ground floor (floor area) is less in that place we have landscape and Parking so it under the first floor but parking is j