Forum quick links
General factors considered when selecting technologies.
NC-2009 PIf2:Project Summary Detailsposted by Jun MA on
Can anybody share the common factors considered when selecting technologies for credits? (E.g. Easy installation, Low-Cost, Multiple credit achievements, etc. )
Pedestrian Walkway
NC-2009 PIf2:Project Summary Detailsposted by Ashley Sadowski on
Hello, We are adding a pedestrian crosswalk to connect the building to the opposite side of the street. This was not required and are hoping to achieve an ID point for including it.
Underground floors...
NC-2009 PIf2:Project Summary Detailsposted by Marcin Gawronski on
We are currently assessing office building which has 2 underground floors. On level -2 there are only: parking, storage, mechanical rooms etc.
Gross Project Square Footage
NC-2009 PIf2:Project Summary Detailsposted by Catherine Blakemore on
When we registered one of our healthcare projects we entered it with a gross project square footage of 14,300. Under the LEED project, the 2nd floor will just a floor and shell, with no finishes o
Rating System?
NC-2009 PIf2:Project Summary Detailsposted by Racha Rachwan on
I'm working on a project containing one Basement, Ground and a first floor, it is a residential building, its building footprint meets the minimum program requirement.
Mechanical Boundary Differs from Overall Project Boundary
NC-2009 PIf2:Project Summary Detailsposted by John Havenstrite on
I am working on a project where the architectural work includes "facelift" work with no HVAC upgrades in roughly half of the scope.
Dormitory as support building
NC-2009 PIf2:Project Summary Detailsposted by ABDUL MUTHALIB MOHAMED on
We would like to register a factory building in Bangladesh. Th built up area of factory building is 2 lakh SFT, Ground level only.
"total gross square footage / gross floor area"
NC-2009 PIf2:Project Summary Detailsposted by Carrie Laurendine on
LEED-NC PIf2 - second row prompts user to fill out "total gross square footage / gross floor area" im confused what they are asking for. and also not sure where to look to research this.
Spoil Area
NC-2009 PIf2:Project Summary Detailsposted by Ashley Sadowski on
I am working on a large dormitory project which requires a "spoil area" on an adjacent lot which accommodates the excess soil in the cut/fill process of regrading the site.
Total number of parking spaces
NC-2009 PIf2:Project Summary Detailsposted by Erin Nuckols on
Hello, I am working on a museum project with an existing building that is not a part of the scope.