Case 3 - On-site electricity storage
NC-v4.1 EAc4:Grid Harmonizationposted by Tine Steen Larsen on
How is the use of batteries evaluated under case 3 "On-site thermal and/or electricity storage: demonstrate that strategy reduces on-peak load by at least 10% as compared to peak electrical dem
0
Utilize emergency generator for peak demand reduction
NC-v4.1 EAc4:Grid Harmonizationposted by Brightworks Sustainability on
Hello,
The project includes fossile fuel based emergency generator. Can we utilize the energency generator to comply with GH credit intent?
1
Mon Oct 21, 2024, 5:52 pm
Case 2 Demand Response Capable Building with a "future" program
NC-v4.1 EAc4:Grid Harmonizationposted by Chris Flint Chatto on
Is case 2 only available to projects with utilities that don't have DR programs? under v4.0, this was clearly the case ("Case 2.
4
Wed May 22, 2024, 11:21 am
Is Case 3 available if Case 1 is?
NC-v4.1 EAc4:Grid Harmonizationposted by Vinh Huynh on
Can Case 3: Load Flexibility and Management Strategies be pursued if there is demand response program available from the local utility?
1
Mon May 18, 2020, 2:18 pm