Case 3 - On-site electricity storage

NC-v4.1 EAc4:Grid Harmonization
posted by  Tine Steen Larsen  on 

How is the use of batteries evaluated under case 3 "On-site thermal and/or electricity storage: demonstrate that strategy reduces on-peak load by at least 10% as compared to peak electrical dem

0

Utilize emergency generator for peak demand reduction

NC-v4.1 EAc4:Grid Harmonization
posted by  Brightworks Sustainability  on 

Hello,

The project includes fossile fuel based emergency generator. Can we utilize the energency generator to comply with GH credit intent?

1
Mon Oct 21, 2024, 5:52 pm

Case 2 Demand Response Capable Building with a "future" program

NC-v4.1 EAc4:Grid Harmonization
posted by  Chris Flint Chatto  on 

Is case 2 only available to projects with utilities that don't have DR programs?  under v4.0, this was clearly the case ("Case 2.

4
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Wed May 22, 2024, 11:21 am

Is Case 3 available if Case 1 is?

NC-v4.1 EAc4:Grid Harmonization
posted by  Vinh Huynh  on 

Can Case 3: Load Flexibility and Management Strategies be pursued if there is demand response program available from the local utility?

1
Mon May 18, 2020, 2:18 pm