Insulation in Interior walls for Vault Spaces in Data Center
NC-v4 EAc2:Optimize energy performanceposted by Rajat Wadhwa on
Hi Everyone,
Regional Priority credit for an L&T credit
CI-v4 LTc1:LEED for neighborhood development locationposted by Cindy Quinn on
Our project is located in an ND Gold certified neighborhood. If we pursue the LEED for ND location credit in leiu of other L&T credits, how can we receive a Regional Priority point for Ac
Zone Secondary Recirculation Fraction
NC-v4 EQp1:Minimum indoor air quality performanceposted by Dave Hubka on
ASHRAE 62.1, Section A1.2.2 states:
Er is less than 1.0 for plenum return systems with secondary recirculation (e.g. fan-powered VAV with plenum return)
Creating Baseline ΗVΑC system selection based on ΑSHRAE 90.1-2010 - Does Ground Floor count as….
NC-v4 EAc2:Optimize energy performanceposted by Konstantina Kalliakoudi on
Hello to all LEED Users,
Ιn our project the Building (nonresidential – 8.000 m2) consists of following levels:
Bioretention Area Calculation
NC-v4 SSc4:Rainwater managementposted by on
I was wondering about how to calculate the Area of bioretention needed to manage expected runoff on the Reference Guide v4 example.
Baseline System for Data center
NC-v4 EAp2:Minimum energy performanceposted by Rajat Wadhwa on
Hi All, I have read som many answers regarding the baseline system for Data centers, Some are saying use system 8 some are saying use system 3 and 4, which one is the right system?
CSR Sample
CI-v4 MRc4:Building product disclosure and optimization - sourcing of raw materialsposted by Edgar Arevalo on
I'm reviewing shop drawings for LEED info. The contractor provides a sample of the BPDO calculator filled out with data that is suppose to reflect information from the documents attached
If the site is walking distance from two separate stops but service the same routes can you count both
NC-v4 LTc5:Access to quality transitposted by David O'Connell on
The site is close to two different stops alexion and BDC but the two stops are serviced by the same routes ? can you count both stops towards the total number of buses i.e.
Non-occupied Garage - Flush required?
NC-v4 EQc4:Indoor air quality assessmentposted by Leanne Conrad on
If we have a separaetly HVAC served storage garage that is quite large and mimininally heated, does this area have to be included in the whole building flush and maintain the higher than normal tem