Forum quick links
Using Existing LEED certified Parking for EV Charger Installation in New Project
NC-v4 LTc8:Green vehiclesposted by sompoche sirichote on
We have a two-phase project: Phase 1 and Phase 2.
Alternative measurement to material costs
NC-v4 MRc3:Building product disclosure and optimization - sourcing of raw materialsposted by Ingrid Pohl on
I'm working on a project where we cannot gather the information of the specific material costs. Is it possible to calculate the percentage based on the weight or the volume instead of by cost?
Pilot credit Design for Indoor Air Quality and Infection Control
NC-v4 INc1:Innovationposted by Emily Purcell on
Didn't see an existing thread for this one, so I'll start one here. I am including this on a couple different projects and getting ready to submit one for review now.
Project vs Lighting boundary
NC-v4 SSc6:Light pollution reductionposted by Bill Swanson on
There appears to still be confusion on the differences between the Project Boundary and the Lighting Boundary. The Project boundary is the same as shown in every other credit.
ny exception for the minimum 5% energy cost saving before renewable energy
NC-v4 EAp2:Minimum energy performanceposted by Moses Chong on
I have a project with 2 building in LEED V4.
Walkable Project Site Innovation credit applicable to a university campus building?
NC-v4 INc1:Innovationposted by Darrah Jakab on
I'm working on a higher ed building in a pedestrian-only area of campus that I believe would be a good candidate for this credit. Has anyone had sucess in achieving this credit for a college c
View Type 1 with non-continuous window glazing
NC-v4 EQc8:Quality viewsposted by Edgar Arevalo on
I have a library that has a reading area with windows surrounding all sides but are separate by the interior wall, which makes the glazing non-continuous. The wall space between windows are a
"Weighted sum of non-roof and roof measures" Issue
NC-v4 SSc5:Heat island reductionposted by Edgar Arevalo on
Under the Summary of Heat Island Reduction Measures, the footnote says "Weighted sum of nonroof and roof measures must be greater than or equal to sum of project paving and roof area for 2 points."
MERV Filters for PM 2.5
NC-v4 EQp1:Minimum indoor air quality performanceposted by Banu Banu on
Dear All,
In our project we have Direct Evaporative coolers . It is a garment production building. In Evaporative coolers, usually the process is mixing of Air & water.
LEED Daylight Simulation Option1 with IES-VE
NC-v4 EQc7:Daylightposted by Mahshid Sedighimoghaddam on
Hello everyone,
We are doing Daylight simulation with IES-VE software in compliance with LEED daylighting Option 1.