Forum quick links
Radius
NC-v4 LTc4:Surrounding density and diverse usesposted by Sylvia Renes on
Hi, How does a 1/4 mile radius around the project site from the project boundary looks like?
Late Start
Hospitality-NC-v4 IPc1:Integrative processposted by Annie Hwang on
We are in the final stages of completing construction documents for a new construction hotel. The owner recently expressed an interest in having the hotel LEED certified.
Historic site
CS-v4 LTc3:High priority siteposted by Jie Xiong on
Hi I am new to V4. There is a question about this credit. On the RG, page 75 further explanation, says that "project may......indicates has significant historic or cultural value".
I believe their is a typo in the reference guide
CI-v4 IPc1:Integrative processposted by Kerry Honsinger on
I believe there is a typo in the ID+C reference guide...My understanding of this credit is that it in no way requires specific site, energy or water improvements, it is just that the possibilities
Process energy cost
NC-v4 EAp2:Minimum energy performanceposted by Charline SEYTIER on
Hi everyone, Reading the v4 reference guide, it seems that the default process energy being 25% of total energy cost for the baseline disappeared from the requirements. Have you also noticed it?
LEED point for products sharing the same EPD
NC-v4 MRc2:Building product disclosure and optimization - environmental product declarationsposted by Anne Lautier on
We are currently conducting an LCA for Office Furniture Workspace Products; in order to present the LCA results in the most flexible way and to facilitate the publication of future EPDs, the EPD re
Minimum light levels are now required
NC-v4 SSc6:Light pollution reductionposted by Bill Swanson on
This has come up on a project and we lost on appeal so I'm sharing this information with everyone. Any area being claimed in the wattage baseline calculation must be illuminated to a minimum light
Sea Water Cooled Chiller Modeling
NC-v4 EAp2:Minimum energy performanceposted by Sefa Sahin on
Dear All, Our project building is located in Istanbul/Turkey. Cooling will be provided by centralised two chillers. There is not a cooling tower.
Heat Island Reduction
EBOM-v4 SSc3:Heat island reductionposted by VISHESH AGARWAL on
Dear All, Can I take option-2: Roof (1 Points) and option-4: Parking Under Cover (1 Points) Simultaneously for achieving 2 points under this category OR we need to use option-3 for targeting the 2
n/a
NC-v4 SSc2:Site development - protect or restore habitatposted by Biao Ma on
I want to know if vertical green wall with native and local plant species, whether or not can conribute the green ratio for option 1.