Forum quick links
Ventilation strategy in a warehouse project
NC-v4 EQp1:Minimum indoor air quality performanceposted by Santiago Avila on
Hi all,
Number of Reviews Allowed
NC-v4 INc1:Innovationposted by Cindy Quinn on
All innovations are now lumped under INc1. If I submit INc1 with a couple strategies in the design preliminary review, and respond to comments in the design final review, will I still be able
Different Baseline HVAC System
NC-v4 EAp2:Minimum energy performanceposted by Amal Venugopal on
Greetings!..
Zero lot line projects
NC-v4 SSc4:Rainwater managementposted by Gustavo De las Heras Izquierdo on
Path 3 states: "manage on site the runoff from the developed site for the 85th percentile ". I guess this requirement was made to exclude the sidewalk from calculations.
LEED Credit impact - On site electricity provision from LPG
NC-v4 EAp2:Minimum energy performanceposted by Robert Yates on
Hi
WEp2 - add shower to awarded credit
NC-v4 WEp2:Indoor water use reductionposted by A&L SUSTENTABILIDADE on
During the Design Review, we have submitted the LT pre-requisite/credit Indoor Water Use Reduction and we have earned a total of 6 points.
Submitting Innovation Credits in Design Phase
CI-v4 INc1:Innovationposted by Kerry Honsinger on
We are going to do the 2 part submittal for review and will submit most of the design credits. On the LEED Online website, Innovation is considered a design credit....
Tenant doesn't install water fixtures - can automatically get 1 point for Option 1 - water analysis?
CI-v4 IPc1:Integrative processposted by Michael on
Hi, My project is interior retail, and they don't install any sanitaryware fixtures in tenant scope.