LEED v4 EBOM - Commissioning

EBOM-v4 EAc2:Existing building commissioning - implementation
posted by  Aber Alvi  on 

A project for which level 2 energy audit had been carried out and implemented more than a year ago, can that energy audit report and the measurement and verification results from the

1
Fri May 25, 2018, 12:26 am

V4 EBOM - Commissioning

EBOM-v4 EAc2:Existing building commissioning - implementation
posted by  Meier Corporate Account  on 

Good Afternoon, Our manufacturing plant was constructed in 2014-2015 and went online in August of 2015.

1
Mon Jun 20, 2016, 9:47 pm