MBCx and Advanced Energy Metering
NC-v4 EAc1:Enhanced commissioningposted by Matt Grace on
Is it agreed that a project can pursue MBCx without first achieving Advanced Energy Metering?
Cheers,
Matt
Is inputting meters in the Whole Building model a MBCx requirement?
NC-v4 EAc1:Enhanced commissioningposted by Lise Dannesboe on
Hi.
Building Envelope CxA
NC-v4 EAc1:Enhanced commissioningposted by Eesmyal Santos-Brault on
Can the envelope consultant of a project also provide Building Envelope commissioning services?
Final Report
NC-v4 EAc1:Enhanced commissioningposted by Colin Grist on
Hello all, I am wondering if there are guidelines for what should be included in the eCx final report. Is there a template or list of items that should be included? Thank you, Colin
BECx on pre-fab steel building
NC-v4 EAc1:Enhanced commissioningposted by Brett Farbstein on
Has anyone had experience with implementing BECx on a pre-fab, steel building?
Enclosure Cx Provider
NC-v4 EAc1:Enhanced commissioningposted by Brett Farbstein on
The project is pursuing v4. A 3rd party Cx provider has been engaged for MEPs.
ASHRAE Guideline 0 2005 or newer?
NC-v4 EAc1:Enhanced commissioningposted by Walter Broner on
For EA prerequisite, the standard for commissioning that is referenced by USGBC (the 2005 edition) is now outdated. Should that standard be used or tne new updated one?
Hiring CxA for Construction other than one hired during Design
NC-v4 EAc1:Enhanced commissioningposted by mohammad Hassan on
Can a different CxA for a project Construction Phase be hired other than the one hired during Design Phase ?
CxA Same for all Paths?
NC-v4 EAc1:Enhanced commissioningposted by Brian Salazar on
Does the CxA need to be the same firm/person for Path 2 and Option 2, as it does for Path 1?
Value of Enhanced Commissioning
NC-v4 EAc1:Enhanced commissioningposted by Hannah Fleck on
I have a client who is asking what the value of pursuing enhanced commissioning versus fundamental.