Forum quick links
Airport External Lighting - Airside
NC-v4 EAp2:Minimum energy performanceposted by Ricardo Sá on
Hi,
System type for baseline in semiheated spaces
NC-v4 EAp2:Minimum energy performanceposted by Ilaria Piong on
Hello,
Data Uploading Issue
NC-v4 EAp2:Minimum energy performanceposted by Muzammal Abbas LEED AP (BD+C) on
Hi,
Off-Site Waste heat
NC-v4 EAp2:Minimum energy performanceposted by Marcus Sheffer on
There were a couple of previous posts on this subject, one from an industrial process and one from a data center that were located outside the LEED project boundary.
District or not district?
NC-v4 EAp2:Minimum energy performanceposted by Ilaria Piong on
I have a building composed of two parts: a warehouse and an office.
Credit to appeal
NC-v4 EAp2:Minimum energy performanceposted by Muzammal Abbas LEED AP (BD+C) on
Hi,
Hope you guy’s will be fine, need your favour and help to clarify my below queries.
Fan demand from Performance Outputs tab exceeds fan power from Air-Side HVAC tab
NC-v4 EAp2:Minimum energy performanceposted by Edgar Arevalo on
I have received this question generated by the LEED v4 Minimum Energy Performance calculator stating "The fan demand (as reported in the Performance Outputs tab) for the baseline and/or proposed ex
v4 DES baseline system modeling for multiple buildings under LEED campus
NC-v4 EAp2:Minimum energy performanceposted by X. Chen on
We are trying to submit to LEED v4 for a site with multiple buildings using LEED campus path. The whole campus is served by central chiller and boiler plant.
Single Zone Variable-Air Volume Controls
NC-v4 EAp2:Minimum energy performanceposted by Gabriela Mena on
We are the CxA of a hospital that have some requirements of meeting positive or negative pressures in some spaces, for this systems the project cannot comply with the requirement of reducing the ai