CO2 sensor issue

CS-2009 IEQc1:Outdoor Air Delivery Monitoring
posted by  G B  on 

Hello all, I would kindly ask for an information please. My HVAC multizone system, looks like this. VAV AHU system (with sensible heat recovery, no mixing) + Fan Coil Units (FCU).

1
Wed Jun 1, 2011, 3:07 pm

ERV serving 3 different tenants

CS-2009 IEQc1:Outdoor Air Delivery Monitoring
posted by  Kristopher Lashley  on 

We have a project where the building is three separate retail tenants all being served by a single ERV that is supplying 100% of the space outdoor air.

1
Mon Jan 23, 2017, 3:10 pm

Outdoor air delivery monitor location?

CS-2009 IEQc1:Outdoor Air Delivery Monitoring
posted by  Mindaugas Mi  on 

Dear Leeduser.com members, who could explain where exactly should the outdoor air delivery monitor should be located? Only at the outdoor intakes?

1
Mon Jan 23, 2017, 2:58 pm

Question about Mechanical Ventilation

CS-2009 IEQc1:Outdoor Air Delivery Monitoring
posted by  Morteza Kasmaei  on 

In IEQc1 Form under MECHANICAL VENTILATION, are those questions about occupied spaces relate to the Base Building (Core and Shell) or to the whole building (including tenant spaces)? Thanks for you

0

What is legally binding language?

CS-2009 IEQc1:Outdoor Air Delivery Monitoring
posted by  Pawel Krawczyk  on 

A copy of the lease agreement that has been provided for review states that the tenants must install CO2 sensors in all densely occupied spaces. For the review team, it is unclear how the provided

3
Thu Jan 21, 2016, 1:12 am

Lease Agreement an option to comply with the credit requirements

CS-2009 IEQc1:Outdoor Air Delivery Monitoring
posted by  Katherine Ann Resurreccion  on 

Hi, We are currently documenting the requirements for this credit and our option in order to comply is to provide a Tenant/Lease Agreement.

3
Sustainability Director, Certifications & Compliance
Jacobs
LEEDuser Expert
469 thumbs up
Thu May 21, 2015, 5:18 pm

HVAC system's capability to accommodate CO2 sensors

CS-2009 IEQc1:Outdoor Air Delivery Monitoring
posted by  CT G  on 

We are working in a CS project without any densely occupied spaces. The project contains VRF units to condition spaces and one fan supplies outdoor air to these units.

2
Sweco
LEEDuser Basic Member
5 thumbs up
Thu Aug 28, 2014, 6:28 pm

CO2 sensors in exhaust air duct

CS-2009 IEQc1:Outdoor Air Delivery Monitoring
posted by  Mathilda Jonsson  on 

Hello I know that the CO2 sensors shall be installed in the breathing zone of the spaces.

2
Environmental Certification Engineer (LEED AP BD+C)
Skanska
LEEDuser Basic Member
32 thumbs up
Tue Aug 26, 2014, 5:02 pm

NO DENSILY OCCUPIED SPACE IS AT OUR PROJECT

CS-2009 IEQc1:Outdoor Air Delivery Monitoring
posted by  Michael E. Edmonds-Bauer  on 

Our project is a CS building with only a few areas within the reach of control of de developer, basically the building staff offices and they will never reach 25 people per 1000 sqft. Does this me

5
Tue Dec 31, 2013, 3:15 pm

summary for mechanically ventilated spaces

CS-2009 IEQc1:Outdoor Air Delivery Monitoring
posted by  BH .  on 

So briefly (for C&S mechanically ventilated spaces): For densly occupied spaces we need: CO2 monitors and i.e.

6