Forum quick links
MR5
CS-2009 MRc4:Recycled Contentposted by Christine Castellano on
this is my first time inputting into LeedOnline - as I cannot find interactive help on that site - I have no idea what to put in the columns where the extraction distance cannot be determined - do
producer declaration
CS-2009 MRc4:Recycled Contentposted by Agnieszka Rylska on
We received a declaration from a material producer stating that the product "contains ca. 80% recycled content" and "we assume that 50% comes from post-consumer".
different concrete classes
CS-2009 MRc4:Recycled Contentposted by Alicja Bieszyńska on
Not sure how it looks in the US, but in Europe we have different concrete classes depending on its strength and - what goes along with that - different material ratio.
Recycled Concrete for Temporary Haul Road
CS-2009 MRc4:Recycled Contentposted by Ralph Bicknese on
The project is using recycled concrete, purchased from an off-site source, to construct a temporary haul road. Can this material be counted towards MRc4 for its recycled content?
Assembly Recycled Content
CS-2009 MRc4:Recycled Contentposted by Angela Saggin on
Hi! I was reading about the assembly recycled content and I didn't quite get it. Using a window as an example, here we can buy the aluminium frame and the glass separately.
Mechanical Insulation
CS-2009 MRc4:Recycled Contentposted by Sarah Gagnon on
I know MEP components are not included in the MR4 credit. What about piping or duct insulation? Insulation is part of Division 7, so I say it should be included.
Aggregating data
CS-2009 MRc4:Recycled Contentposted by Eeshoo Rehani on
One LEED site boundary has two individual LEED projects that are under construction under one contract by the same GC.
Recycled Water in Concrete and SCMs
CS-2009 MRc4:Recycled Contentposted by Ward Miller on
The Reference Guide language related to SCMs in concrete gives project teams the choice whether to include SCMs as a percentage of the entire concrete or separate them out (pg.
MR Calcuation Cost
CS-2009 MRc4:Recycled Contentposted by Lilian Seow on
Re: 2009 CS For both options - Total Construction Cost and Default 45% - are taxes included?
How do we address non-certifiable Parking Garage ?
CS-2009 MRc4:Recycled Contentposted by natalie tan on
HI, I previously posted a similar message in the MPR forum but there was no reply and am reposting it here as it pertains to MRc4/c5/c6.