Post a question or comment
Credit Filters
Enhanced Commissioning
Filter by location
Forum
Topic
Replies
Recent
1
Tue Nov 16, 2010, 4:59 pm

Enhanced Cx EP

CS-2009 EAc3:Enhanced Commissioning
posted by  David Edenburn  on 

For exemplary performance for a CS project, we can commission the tenant spaces.

1
Wed Oct 10, 2012, 9:17 pm

high efficiency motors

CS-2009 EAc3:Enhanced Commissioning
posted by  Afonso Cardoso  on 

I would like to know if high efficiency motor's verification is part of fundamental commissioning or even enhanced commissioning? If don't, where does it fit? Which credit?

1
Fri Aug 31, 2012, 1:50 pm

Monitoring Based Commissioning

CS-2009 EAc3:Enhanced Commissioning
posted by  Afogreen Build  on 

Hi guys! I have a question regarding monitoring based commissioning. Based on this credit what are the minimum required meters to be installed in the building that will be monitored and commission

1
Fri Oct 21, 2016, 6:02 pm

Commissioning innovation point

CS-2009 EAc3:Enhanced Commissioning
posted by  Magnus Stagnäs  on 

The reference guide states that CS projects requiring both fundamental and enhanced commissioning for all tenant spaces may be considered for an innovation point.

1
Tue Nov 29, 2011, 1:40 pm

EAc3 Exemplary Performance

CS-2009 EAc3:Enhanced Commissioning
posted by  BH .  on 

Thanks for all descriptions and comments related to differences beween EAp1 and EAc3. I`m still confused about Exemplary Performance and it`s "comprehensive envelope commissioning".

1
Thu Aug 16, 2012, 7:41 pm

a question about DES option 1

CS-2009 EAc3:Enhanced Commissioning
posted by  Shenhao Li  on 

Hello! I have a question about EAc3 for DES system.

4
Wed Jul 27, 2016, 11:23 pm

CxA contract

CS-2009 EAc3:Enhanced Commissioning
posted by  Agnieszka Rylska  on 

Can Commissioning Authority be contracted through the design firm (architects) as part of the LEED certification contract (CxA would be an employee of the LEED consultant company) and not by the ow

2
LEED Fellow
Integrated Design + Energy Advisors, LLC
LEEDuser Expert
377 thumbs up
Wed Jul 27, 2016, 2:35 am

Qualifying Scope for Enhanced Cx

CS-2009 EAc3:Enhanced Commissioning
posted by  Alexis Voeltner  on 

I am working on a project where the only permanently installed system that could be commissioned under the core & shell scope is the exterior lighting controls.

3
Sustainability Project Manager
UL Solutions
LEEDuser Expert
11 thumbs up
Sat Jul 11, 2015, 10:08 pm

Systems manual

CS-2009 EAc3:Enhanced Commissioning
posted by  Michael E. Edmonds-Bauer  on 

We are done with our commissioning process and almost ready to submit for preliminary construction review, however the systems manual (Upload EAc3-1) is develop in Spanish language since it is the

4
Tue Mar 24, 2015, 10:58 pm