Is EAc2 affected by the use of the ACP calculation for EAc1?
CS-2009 EAc2:On-site Renewable Energyposted by Charlie Christenson on
Working on a core & shell project that is planning to install a PV system sized to offset 1% of total building energy cost.
Reference for the building annual energy cost
CS-2009 EAc2:On-site Renewable Energyposted by Ricardo Sá on
In a Core&Shell project, the percentage of renewable energy integration shall be refered to the total building energy use (including tenants areas) or only to core and shell energy use ?
PV System as part of a Master Site
CS-2009 EAc2:On-site Renewable Energyposted by Ben Tucker on
Does anyone have any experience submitting for EAc2 as part of a Master Site? Our project is a campus project that will contain three buildings.
Biomass from energetic crops
CS-2009 EAc2:On-site Renewable Energyposted by BH . on
Hi, does LEED recognize the biomass from energetic crops such like: -short rotation coppice (Poplar and willow include) -Grasses and non-woody energy crops (Miscanthus and Hemps included) Tha
How many credit points does one get by offsetting 7%.
CS-2009 EAc2:On-site Renewable Energyposted by Tuana Papile on
By using on-site renewable energy for 7% of the total energy, do we get now 7 points compared to the 4 points for NC? Thank you
CHP biofuel certifications
CS-2009 EAc2:On-site Renewable Energyposted by Marcello Polverino on
Hi LEED-User, I would like to know which documents I need to provide to the USGBC for a block heat and power plant fueled with biogas? Thanks Best wishes from Hanover (germany)
Geothermal (Sometimes you're in, sometimes you're out!)
CS-2009 EAc2:On-site Renewable Energyposted by Katie Mesia on
We are in schematic design on a CS project. The project will have underground parking and will use piles as a foundation.
How to calculate %
CS-2009 EAc2:On-site Renewable Energyposted by Emmanuel Pauwels on
The reference for the calculation is total energy cost. The output of an array of PV panels is in kwh.