In a Core&Shell project, the percentage of renewable energy integration shall be refered to the total building energy use (including tenants areas) or only to core and shell energy use ?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Marcus Sheffer
LEED Fellow7group / Energy Opportunities
LEEDuser Expert
5912 thumbs up
September 7, 2012 - 10:23 am
It is based on the whole building energy use.
Maya Karkour
EcoConsulting872 thumbs up
March 24, 2014 - 12:16 pm
Hi Marcus,
Regarding this query, why does the LEED Reference guide "CS Appendix 4" list EA Credit 2 under "Case B" credits?
Case B credits are defined as:
"Submittal documentation for Case B credits need only include data from the Core & Shell project scope. If the project team wishes to claim performance improvements based on anticipated tenant work, such data must be supported by tenant sales and/or lease agreements."
Marcus Sheffer
LEED Fellow7group / Energy Opportunities
LEEDuser Expert
5912 thumbs up
March 24, 2014 - 12:59 pm
So it is actually based on the whole building energy cost (not use as I indicated).
Appendix 4 refers to tenant improvements. If renewables are being claimed as part of work to be done by the tenants then it would be a Case B credit.
Maya Karkour
EcoConsulting872 thumbs up
March 24, 2014 - 1:02 pm
Oh okay, makes sense. Thanks Marcus!