Need help, using new v2009v4_Minimum IAQ Calculator_v03
CI-2009 IEQp1:Minimum indoor air quality performanceposted by Edgar Arevalo on
After adding all the values for four floors I'm working on, I then input the design OA intake flow for each floor's AHU. In the summary tab, 3 out of 4 of the Zone systems meet the required OA int
Single Zone served by 2 HVAC systems
CI-2009 IEQp1:Minimum indoor air quality performanceposted by Nandana Kumar on
Hi, In our project, a particular zone (Board Room) is being served by 2 systems: central chiller plant through an AHU & by Cassette Units.
IEQp1: Minimum Indoor Air Quality Performance
CI-2009 IEQp1:Minimum indoor air quality performanceposted by Arslan Faisal on
We are working on a plaza which have office spaces. we submit this project. But in the review report they asking the following documents.
IEQp1 Compliance ?
CI-2009 IEQp1:Minimum indoor air quality performanceposted by George Bender on
Office floor of a high rise building trying to obtain LEED sliver. Floor is served by AHU, which serves 30 other floors not in scope. VAV's serve multiple zones on this floor.
IEQp1 Design Review told me I have multizone not single
CI-2009 IEQp1:Minimum indoor air quality performanceposted by Kasandra Martin on
I have roof top units. Each serves several rooms. One system serves a single room with single thermostat.
Transfer Air for IEQp1 achievement
CI-2009 IEQp1:Minimum indoor air quality performanceposted by Ricardo Sá on
Hello, I'm currently working on a project of a huge supermarket. The building has warehouses and storage rooms.
RE:62MZ calc. spreadsheet Vdzd & Ds inputs
CI-2009 IEQp1:Minimum indoor air quality performanceposted by Bobby Ghataura on
In the 62MZ calc, i created zones that have heating and potentially critically zones, but im having an issue with the results; for Vdzd, i enter the airflow rate that corresponds to the minimum VAV
Multi-zone system when single AHU supplying OA to FCUs?
CI-2009 IEQp1:Minimum indoor air quality performanceposted by Poorva Keskar on
We have 2 AHUs supplying OA to individual FCUs via a separate duct as per ASHRAE 62 intake requirement. The mixing occurs at the individual FCUs and then supplied to the zone.
IEQp1 using indoor packaged DX units
CI-2009 IEQp1:Minimum indoor air quality performanceposted by Edgar Arevalo on
I'm in a bit of a funk. I have a office space that populates two floors of a building.