Cooling Tower for Back-up Diesel Generators (DG)

EBOM-2009 WEc4:Cooling Tower Water Management
posted by  Anshul Chawla  on 

The project site has 3 cooling towers of 215 ton capacity each. These cooling towers serve the HVAC system of the building and are operational for 8-10 hrs on all working days.

1
Tue Dec 20, 2011, 4:46 pm

Pursuing this Credit for New Construction

EBOM-2009 WEc4:Cooling Tower Water Management
posted by  Michael Angell  on 

Would this credit be available as an ID credit under a project going for new construction? Or is there already a like credit that addresses these parameters?

1
Fri Oct 21, 2011, 9:36 pm

WE Credit 4.2: Cooling Tower Water Management- non potable

EBOM-2009 WEc4:Cooling Tower Water Management
posted by  satheesh M  on 

The project’s cooling requirement is being met by both chiller plant inside the project boundary as well as the chiller plant in the Building Owned DES.

1
Tue Dec 1, 2015, 4:07 pm

One Conductivity Meter for Multiple towers

EBOM-2009 WEc4:Cooling Tower Water Management
posted by  Jessica Hawley  on 

On our project building there is only one system meter. All cooling towers are interconnected with a single header which is monitored by the conductivity meter.

1
Fri Oct 21, 2011, 9:48 pm

Using Rainwater for Cooling Tower Make-up

EBOM-2009 WEc4:Cooling Tower Water Management
posted by  Kevin Krejci  on 

Thinking of doing a feasability study on using rainwater from garage run-off for cooling tower make-up. Has anyone been down this road and is willing to share challenges / successes?

1
Mon Sep 3, 2012, 2:18 pm

DEC - EBOM

EBOM-2009 WEc4:Cooling Tower Water Management
posted by  babu rajendran  on 

My project getting chilled water from District energy center which has cooling towers.

1
Wed Dec 10, 2014, 5:35 pm

Non Potable Water Source Use

EBOM-2009 WEc4:Cooling Tower Water Management
posted by  Rajesh Ghorla  on 

What QC process can be added to identify variances from Standard Approach and what measures can be take.

1
Wed Jul 31, 2013, 4:27 pm

WE 4.1 TEMPLATE

EBOM-2009 WEc4:Cooling Tower Water Management
posted by  Adriana Hansen  on 

In our project the towers has the following water cooling consumption during the Performance Period: Potable: KGALI 52.16 (4% of total) Non Potable: KGALI 346.71 (96% of total) TOTAL: 398.87 In m

1
Sat Apr 23, 2011, 1:15 pm

Drycoolers

EBOM-2009 WEc4:Cooling Tower Water Management
posted by  WAGNER OLIVEIRA SILVA  on 

We work on a project that has Drycoolers, all water user is non-potable. Since there is no closed loop and make up water this system there no treatment. Can we pursue both 4.1 and 4.2 credits?

3
Default Avatar
Environmental and Energy Consultant
WSP Environmental Sweden
LEEDuser Basic Member
6 thumbs up
Wed May 17, 2017, 9:50 am

Would an Evaporative Cooler Be Considered a Cooling Tower?

EBOM-2009 WEc4:Cooling Tower Water Management
posted by  Michelle Bracewell-Musson  on 

We have 2 cooling towers and 4 evaporative coolers (Climate Wizard). Would these all be considered cooling towers with reference to this credit?

5
Mon Jun 20, 2016, 3:04 pm