Cooling Tower for Back-up Diesel Generators (DG)
EBOM-2009 WEc4:Cooling Tower Water Managementposted by Anshul Chawla on
The project site has 3 cooling towers of 215 ton capacity each. These cooling towers serve the HVAC system of the building and are operational for 8-10 hrs on all working days.
Pursuing this Credit for New Construction
EBOM-2009 WEc4:Cooling Tower Water Managementposted by Michael Angell on
Would this credit be available as an ID credit under a project going for new construction? Or is there already a like credit that addresses these parameters?
WE Credit 4.2: Cooling Tower Water Management- non potable
EBOM-2009 WEc4:Cooling Tower Water Managementposted by satheesh M on
The project’s cooling requirement is being met by both chiller plant inside the project boundary as well as the chiller plant in the Building Owned DES.
One Conductivity Meter for Multiple towers
EBOM-2009 WEc4:Cooling Tower Water Managementposted by Jessica Hawley on
On our project building there is only one system meter. All cooling towers are interconnected with a single header which is monitored by the conductivity meter.
Using Rainwater for Cooling Tower Make-up
EBOM-2009 WEc4:Cooling Tower Water Managementposted by Kevin Krejci on
Thinking of doing a feasability study on using rainwater from garage run-off for cooling tower make-up. Has anyone been down this road and is willing to share challenges / successes?
DEC - EBOM
EBOM-2009 WEc4:Cooling Tower Water Managementposted by babu rajendran on
My project getting chilled water from District energy center which has cooling towers.
Non Potable Water Source Use
EBOM-2009 WEc4:Cooling Tower Water Managementposted by Rajesh Ghorla on
What QC process can be added to identify variances from Standard Approach and what measures can be take.
WE 4.1 TEMPLATE
EBOM-2009 WEc4:Cooling Tower Water Managementposted by Adriana Hansen on
In our project the towers has the following water cooling consumption during the Performance Period: Potable: KGALI 52.16 (4% of total) Non Potable: KGALI 346.71 (96% of total) TOTAL: 398.87 In m
Drycoolers
EBOM-2009 WEc4:Cooling Tower Water Managementposted by WAGNER OLIVEIRA SILVA on
We work on a project that has Drycoolers, all water user is non-potable. Since there is no closed loop and make up water this system there no treatment. Can we pursue both 4.1 and 4.2 credits?
Would an Evaporative Cooler Be Considered a Cooling Tower?
EBOM-2009 WEc4:Cooling Tower Water Managementposted by Michelle Bracewell-Musson on
We have 2 cooling towers and 4 evaporative coolers (Climate Wizard). Would these all be considered cooling towers with reference to this credit?