On our project building there is only one system meter. All cooling towers are interconnected with a single header which is monitored by the conductivity meter. Will this configuration be acceptable for this credit or does USGBC require separate meters for each tower? Thanks for the help!
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Brittany Bliffen
Sustainability ManagerYR&G
39 thumbs up
October 21, 2011 - 5:48 pm
From my experience, that should be fine. Anybody else have thoughts?