4.Incorporate the measures from 2.1(b) and (c), above, into project documents (drawings, specifications, and/or scopes of work, as appropriate).
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11478 thumbs up
November 25, 2013 - 11:32 am
David, the list in the credit language above under subhead 2.1 is numbered 1–6 in the USGBC credit language. This appears to be an error (probably related to web publishing of the credit requirements), and the list under 2.1 should be labeled "a" through "e." Therein lie the measures you are looking for.
Asa Foss
LEED for Homes Techincal DevelopmentUS Green Building Council
LEEDuser Expert
48 thumbs up
November 25, 2013 - 12:50 pm
Tristan is correct. We will work on correcting that ASAP so that no one else will be confused.
Thanks for bringing this up!
Batya Metalitz
Technical Director, LEEDUSGBC
LEEDuser Expert
318 thumbs up
November 25, 2013 - 1:23 pm
The numbering has been corrected.