Post your questions on this credit in the forum, and click on the credit language tab to review to the LEED requirements.
Credit language
© Copyright U.S. Green Building Council, Inc. All rights reserved.
Requirements
Note: USGBC and its representatives are responsible only for verifying the completion of LEED for Homes requirements; such verification in no way constitutes a warranty as to the appropriateness of the selected durability measures or the quality of implementation (see Disclaimer, page 2).Prerequisites
2.1 Durability planning. Prior to construction, the project team shall do the following:- Complete the Durability Risk Evaluation Form to identify all moderate and high-risk durability issues for the building enclosure.
- Develop specific measures to respond to those issues.
- Identify and incorporate all the applicable indoor moisture control measures listed in Table 1.
- Incorporate the measures from 2.1(b) and (c), above, into project documents (drawings, specifications, and/or scopes of work, as appropriate).
- List all the durability measures and indicate their locations in the project documents in a durability inspection checklist. Include the checklist in project documents for use in verification.
Table 1
Location or equipment | Required moisture control measure |
---|---|
Tub, showers and spa areas | Use nonpaper-faced back board on walls |
Kitchen, bathroom, laundry rooms, and spa areas | Use water-resistant flooring; do not install carpet. |
Entryway (within 3 feet of exterior door) | Use water-resistant flooring; do not install carpet. |
Tank water heater in or over living space | Install drain and drain pan |
Clothes washer in or over living space | Install drain and drain pan, or install accessible single-throw supply valve. |
Conventional clothes dryer | Exhaust directly to outdoors |
Condensing clothes dryer | Install drain and drain pan |
What does it cost?
Cost estimates for this credit
On each BD+C v4 credit, LEEDuser offers the wisdom of a team of architects, engineers, cost estimators, and LEED experts with hundreds of LEED projects between then. They analyzed the sustainable design strategies associated with each LEED credit, but also to assign actual costs to those strategies.
Our tab contains overall cost guidance, notes on what “soft costs” to expect, and a strategy-by-strategy breakdown of what to consider and what it might cost, in percentage premiums, actual costs, or both.
This information is also available in a full PDF download in The Cost of LEED v4 report.
Learn more about The Cost of LEED v4 »Frequently asked questions
See all forum discussions about this credit »Documentation toolkit
The motherlode of cheat sheets
LEEDuser’s Documentation Toolkit is loaded with calculators to help assess credit compliance, tracking spreadsheets for materials, sample templates to help guide your narratives and LEED Online submissions, and examples of actual submissions from certified LEED projects for you to check your work against. To get your plaque, start with the right toolkit.
© Copyright U.S. Green Building Council, Inc. All rights reserved.
Requirements
Note: USGBC and its representatives are responsible only for verifying the completion of LEED for Homes requirements; such verification in no way constitutes a warranty as to the appropriateness of the selected durability measures or the quality of implementation (see Disclaimer, page 2).Prerequisites
2.1 Durability planning. Prior to construction, the project team shall do the following:- Complete the Durability Risk Evaluation Form to identify all moderate and high-risk durability issues for the building enclosure.
- Develop specific measures to respond to those issues.
- Identify and incorporate all the applicable indoor moisture control measures listed in Table 1.
- Incorporate the measures from 2.1(b) and (c), above, into project documents (drawings, specifications, and/or scopes of work, as appropriate).
- List all the durability measures and indicate their locations in the project documents in a durability inspection checklist. Include the checklist in project documents for use in verification.
Table 1
Location or equipment | Required moisture control measure |
---|---|
Tub, showers and spa areas | Use nonpaper-faced back board on walls |
Kitchen, bathroom, laundry rooms, and spa areas | Use water-resistant flooring; do not install carpet. |
Entryway (within 3 feet of exterior door) | Use water-resistant flooring; do not install carpet. |
Tank water heater in or over living space | Install drain and drain pan |
Clothes washer in or over living space | Install drain and drain pan, or install accessible single-throw supply valve. |
Conventional clothes dryer | Exhaust directly to outdoors |
Condensing clothes dryer | Install drain and drain pan |