Involve contractors in an acoustics discussion before construction begins to help them understand the importance of specific designs and drawing details.
Prior to issuing Certificate of Occupancy, ensure that all remediation efforts have been completed, properly documented, and submitted to proper authorities.
Make final calculations of the estimated building energy loads. Confirm that renewable energy generation capacity is 1% of building energy, at minimum for the LEED credit, or that the project’s goals are met.
Coordinate the project schedule to account for installation and connection requirements of the renewable energy systems. Often, when unfamiliar with the system, the construction team does not account for the additional time and interaction required with steel, electrical, mechanical and plumbing subcontractors.