The language of LEED V4.1 says that project either collect one year waste data or waste analysis. Does it means, the waste analysis is an audit which can be done based on less then 1 year collection record, and it would still be applicable?

2

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Thu, 06/29/2023 - 21:32

Hi Shashank Did you ever get a response on this? 

Thu, 07/20/2023 - 00:36

This is correct. Projects need a minimum of 12 months of waste data and if that is not available, then a waste audit may be conducted following the requirements from v4 language.