Hey group,
I'm part of the contractor team on a large commercial project pursuing LBC v3.1 Petal Certification, with one of those petals being materials. This requires the team to meet Imperative 10 Red List.
The ownership group has taken the responsibility of red list vetting as a task of their own. The construction team is to give products to the ownership group to vet for compliance and advise on the application & cost of product alternatives when the preferred product isn't compliant.
I'm looking to see if any of you contractors have had experience with the Red List, and lessons learned you can share (spec sections that require extra attention, processing ideas, etc). I'd appreciate any feedback.