Hi, if existing building materials, such as concrete as an example, is removed from site during demolition, is there benefits if this was processed offsite and reused in there of gravel for the same project or other projects. Where would this slot in in terms of LEED ? .
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11477 thumbs up
October 15, 2019 - 7:25 am
Yes, this would be considered diversion from the landfill, and would be beneficial for earning this credit.
Catarina Costa Goncalves
2 thumbs up
April 23, 2024 - 11:47 am
Would be the same for soil and stones that were extracted during demolition but reused in the project construction? They will be added to waste calculated and contribute to waste diverted from landfill right?