Forum discussion

Pilot-Credits WEpc94:No Cooling Tower

Documenting WEpc94 - No Cooling Tower

We are pursing certification of Japanese company's headquarter office. Our project building has both air-cooled heat pump system and geothermal heat pump system with many bore holes that collect heat in winter and reject heat in summer. It does not include a cooling tower and does not use the latent heat of the evaporative cooling of water. Additionally, the project does not receive any cooling from a District cooling system. The baseline system designated by ASHRAE 90.1-2010 Appendix G Table G3.1.1 is system 7.

Our concern is that the demonstration of the above will be sufficient to achieve the documentation requirements for the credit. Does anyone answer our question?

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Fri, 10/11/2019 - 14:59

Hello Noriko,  You can apply for the No Cooling Tower pilot alternative compliance path. You need to include the following as part of the submittals: a. A copy of the Pilot Credit registration confirmation email b. A copy of the Pilot Credit survey confirmation email c. Documentation showing that the project is designated as systems 7 or 8 under ASHRAE 90.1-2010 Appendix G Table G3.1.1 d. Documentation (site plan or mechanical system plan, energy model or other) showing that the project design case does not include a cooling tower or other system that uses the latent heat of the evaporative cooling of water, and is not connected to a District cooling system. This should help you to meet the requirement with this approach. Hope it helps!

Add new comment

To post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.