Hi Everyone!....just joining the LEED forum family.
I am evaluating a case for LEED Campus Cert. in order to prepare a service proposal, but complex conditions are encountered in the site. I just read the MPR and the 2010 AGMBC, and while reading previous comments on this website related to the subject, some things are clear, but some are more confusing.
Questions:
1- Whether the pre-approved Master Site credits are to be applied to each individual LEED project certification, when applicable to one or more projects, or these credits are consumed when applied to the first LEED project certification?
2- A very particular condition in the site is as follow: Building A (BA) is a 7 story existing tower (only 1st and 3rd floor are owned ), Building C (BC) is a 4 story existing building in operation. As an in-fill building, a third will be inserted occupying the opened space separating BA and BC, named Building B (BB), a three story new construction building, intended for leed certification. BB is attached to both BA and BC, and will be connected to both in the 1st and 3rd floor with BA and connected through 1st floor with BC. How should LEED certification process be approached in this case where a new building connects to and facilities are shared with adjacent buildings?
At this moment i have considered to use LEED-BD&C. Please correct me if i am wrong. I will greatly appreciate any opinion or suggestion to solve this uncertain case.
AM
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11478 thumbs up
November 14, 2011 - 12:19 am
The master credits are not "consumed" -- they can be applied to multiple projects.
For your question on the attached buildings, have you checked out the Minimum Program Requirements supplemental guidance? There are some great tips in there. Let us know if you have more specific questions relative to that guidance.
Hernando Miranda
OwnerSoltierra LLC
344 thumbs up
April 30, 2012 - 12:05 pm
On-Site Renewable Energy is one case of a credit that is "consumed" by the individual projects.
Assuming a project has 100kW of site-wide photovoltaic systems, and it has two LEED projects. The 100kW is split between them. If project one "consumes" 50kW and project two 30kW then 80kW is used up.
Of the total site-wide system 20kW would not be "consumed." The owner has the option to pursue a third LEED project and use the 20kW they have left over.