Dear Concern:-

Is Building Envelope Commissioning required for Major Renovation project?
We are working on a factory building where interior floor plan and core MEP system were renovated.
No modifications were done on building envelope

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Thu, 01/11/2018 - 14:41

Samy, envelope commissioning is optional for this credit. If it doesn't fit your project, you could skip it, though you won't earn maximum points. Commissioning an existing envelope can be done and can bring benefits, though again if it's out of scope and there isn't interest in taking it on, you don't need to do so.

Wed, 01/24/2018 - 20:45

One augment to Tristan's reply...you should still address the envelope in the OPR, which is required in the prerequisite. It is also good to at least state what the envelope is, its condition and performance, and describe why it was not part of the scope of the project.